BART Silicon Valley Phase II extension

Santa Clara Valley Transportation Authority · San Jose and Santa Clara, California

Enabling construction under way, federal grant agreement still ahead

A six-mile BART extension, mostly in a single-bore tunnel, from Berryessa through downtown San Jose to Santa Clara.

Show on the map: BART Silicon Valley Phase II extension

Next gate

Rebaseline presented

December 2026

VTA planned to update the Oversight Committee on the rebaseline schedule and cost in December 2026, with a further meeting in January 2027.

Every step so far, and what comes next

  1. DoneFebruary 2024

    Baseline adopted

    VTA adopted the baseline budget and schedule submitted to FTA for entry into New Starts Engineering.

  2. DoneSeptember 2026

    West Portal work advancing

    West Portal construction continued and was anticipated to finish earlier than planned. Stage 2 work also continued.

  3. DoneOct 23, 2026

    Station-site demolition finished

    All 11 buildings at the 28th Street / Little Portugal station site had been demolished above ground. A parking-lot handover at Diridon was completed on Oct 16.

  4. NextDecember 2026

    Rebaseline presented

    VTA planned to update the Oversight Committee on the rebaseline schedule and cost in December 2026, with a further meeting in January 2027.

  5. ExpectedJanuary 2027

    Utility relocation at the East Portal

    VTA's schedule after preparatory work that was set to start on Oct 26, 2026.

  6. ExpectedSecond quarter of 2037

    Target revenue service

    VTA's target date. FTA's risk-assessed date is the first quarter of 2039.

Worth knowing

Last checked Nov 23, 2026. We add a step when it happens and link the source.