BART Silicon Valley Phase II extension
A six-mile BART extension, mostly in a single-bore tunnel, from Berryessa through downtown San Jose to Santa Clara.
Show on the map: BART Silicon Valley Phase II extension
- Baseline budget$12.746 billion, the mid-2024 FTA-eligible baselineSanta Clara Valley Transportation Authority, Oct 28, 2026
- Spent so farAbout $2.17 billion paid through September 2026, against $2.90 billion committedSanta Clara Valley Transportation Authority, Oct 28, 2026
- Service targetVTA's target is the second quarter of 2037; FTA's risk-assessed date is the first quarter of 2039Santa Clara Valley Transportation Authority, Oct 28, 2026
- Federal share$5.1 billion after a Full Funding Grant Agreement, with a funding gap still to closeSanta Clara Valley Transportation Authority, Oct 28, 2026
Next gate
Rebaseline presented
December 2026
VTA planned to update the Oversight Committee on the rebaseline schedule and cost in December 2026, with a further meeting in January 2027.
Every step so far, and what comes next
-
DoneFebruary 2024
Baseline adopted
VTA adopted the baseline budget and schedule submitted to FTA for entry into New Starts Engineering.
Source: Santa Clara Valley Transportation Authority, Oct 28, 2026
-
DoneSeptember 2026
West Portal work advancing
West Portal construction continued and was anticipated to finish earlier than planned. Stage 2 work also continued.
Source: Santa Clara Valley Transportation Authority, Oct 28, 2026
-
DoneOct 23, 2026
Station-site demolition finished
All 11 buildings at the 28th Street / Little Portugal station site had been demolished above ground. A parking-lot handover at Diridon was completed on Oct 16.
Source: Santa Clara Valley Transportation Authority, Oct 28, 2026
-
NextDecember 2026
Rebaseline presented
VTA planned to update the Oversight Committee on the rebaseline schedule and cost in December 2026, with a further meeting in January 2027.
Source: Santa Clara Valley Transportation Authority, Oct 28, 2026
-
ExpectedJanuary 2027
Utility relocation at the East Portal
VTA's schedule after preparatory work that was set to start on Oct 26, 2026.
Source: Santa Clara Valley Transportation Authority, Oct 28, 2026
-
ExpectedSecond quarter of 2037
Target revenue service
VTA's target date. FTA's risk-assessed date is the first quarter of 2039.
Source: Santa Clara Valley Transportation Authority, Oct 28, 2026
Worth knowing
- A cost and schedule rebaseline is under review, with updates planned for December 2026 and January 2027. The $12.746 billion figure may change.
- With approved changes, the September 2026 cost table showed $12.715 billion against the mid-2024 baseline.
- The Full Funding Grant Agreement date is listed as to be determined.
- Dates after the rebaseline are subject to change.
Last checked Nov 23, 2026. We add a step when it happens and link the source.
Tracking saves to this device only. No account, no email, free.