Track your favorite projects · Data centers
Beale Infrastructure De Soto data center campus
A planned four-building hyperscale campus next to the Panasonic plant in De Soto, with an estimated $3 billion development value and official city confirmation that grading and early site preparation are underway.
Show on the map: Beale Infrastructure De Soto data center campus
- InvestmentBeale's April 28, 2026 announcement put the estimated development value at $3 billion at full build-out, the figure used on the map. The City of De Soto's project page, reviewed on November 23, 2026, instead estimates private investment at approximately $3.1 billion. This page keeps the map figure and records the city's estimate in the caveatsBeale Infrastructure, Apr 28, 2026
- ScopeThe April 28, 2026 company release said the first phase will include at least two facilities, and that full build-out is expected to encompass four buildings and more than one million square feet, with a long-term technology tenant lease. Beale said all major project infrastructure, including power delivery, water systems, and site improvements, will be privately funded, with electric service from Evergy. The site is previously designated industrial land adjacent to the Panasonic battery plantBeale Infrastructure, Apr 28, 2026
- Location and jobsThe City of De Soto places the campus at the Flint Commerce Center, at 103rd Street and Edgerton Road. Beale's location page says the campus is south of K-10. The company said the first phase will add hundreds of construction jobs and 50 operational rolesCity of De Soto, Kansas, Nov 23, 2026
- StatusBeale's April 28, 2026 release said the first phase would break ground in May and that site preparation activities would begin that month. The company's De Soto page, reviewed on November 23, 2026, lists a spring 2026 construction start and 2029 for Phase 1 completion. The City of De Soto's project page says the Phase 1 site plan for Buildings 1 and 2 has received conditional approval, grading and early site preparation activities are underway, construction is targeted to begin in 2026, and phased development is expected to run through approximately 2035City of De Soto, Kansas, Nov 23, 2026
Next gate
Phase 1 construction and completion
Construction targeted 2026; Phase 1 completion listed as 2029 on the company page
The City of De Soto says construction is targeted to begin in 2026, with grading and early site preparation already underway. Beale's location page lists Phase 1 completion in 2029.
Every step so far, and what comes next
-
DoneApril 28, 2026
Campus announced at an estimated $3 billion
Beale announced the first phase of the De Soto campus, with an estimated $3 billion development value at full build-out and a planned May groundbreaking.
-
DoneAs of the city page reviewed November 23, 2026
Grading and early site preparation underway
The City of De Soto said the Phase 1 site plan has conditional approval and that grading and early site preparation activities are underway.
-
Next2026
Construction targeted to begin
The city page says construction is targeted to begin in 2026, and Beale's location page lists a spring 2026 construction start.
Worth knowing
- The map still lists this pin as announced. The tracker stage is site work underway because the City of De Soto's official project page says grading and early site preparation activities are underway. That is not treated here as a separately dated building groundbreaking.
- The city's approximately $3.1 billion private-investment estimate is official but is not the map figure. This page keeps the company's $3 billion estimated development value from April 28, 2026.
- A later trade-press report that work had started by July 2, 2026 was not used as a source.
- Industrial Revenue Bond incentives and payment-in-lieu-of-tax terms described on the city page are not treated as part of the capital budget.
Go deeper
Last checked Nov 23, 2026. We add a step when it happens and link the source.