Track your favorite projects · Energy
Black Hills generation for Google Cheyenne data center
An announced $1.8 billion plan to build 564 megawatts of company-owned natural gas generation at Cheyenne Prairie Generating Station to help serve a planned Google data center, with generation construction expected to begin in 2027.
Show on the map: Black Hills generation for Google Cheyenne data center
- InvestmentBlack Hills Corp.'s October 6, 2026 official release, filed with the SEC as Exhibit 99.1, says the company plans to invest $1.8 billion between 2027 and 2029 to construct 564 megawatts of nameplate company-owned natural gas generation at the existing Cheyenne Prairie Generating Station, the figure used on the map. The same release describes additional, separately identified items that are not used to replace or add to that figure, including about $2.4 billion of unlevered free cash flow through 2048 net of the $1.8 billion of capital expenditures, about $150 million of expected net income in 2030, $399 million of refundable advances from Google for long-lead equipment, and anticipated additional transmission investment.Black Hills Corp. (SEC Exhibit 99.1), Oct 6, 2026
- Agreements and serviceThe company said it signed definitive agreements effective September 30, 2026, with terms through 2048, to serve a planned Google data center in Cheyenne. Black Hills will provide up to 590 megawatts of grid-connected energy service through company-owned generation and market energy, and will manage about 2.1 gigawatts of Wyoming-based, third-party contracted resources through a privately managed microgrid. Energy service is planned to begin in late 2027 and ramp to the project's peak load in 2030. The company expects to begin earning a return on its generation investment when construction begins in 2027.Black Hills Corp. (SEC Exhibit 99.1), Oct 6, 2026
- Regulatory statusThe official release says a Robinson substation certificate of public convenience and necessity was approved in May 2026, an industrial siting permit for the Cheyenne Prairie expansion was filed in July 2026, and an air quality permit for the expansion was approved in August 2026. Additional transmission filings are described as separate and are not included in the $1.8 billion generation figure.Black Hills Corp. (SEC Exhibit 99.1), Oct 6, 2026
Next gate
Generation construction expected to begin
2027, according to the October 6, 2026 official release
Black Hills said it plans to invest $1.8 billion between 2027 and 2029 and expects to begin earning a return on the generation investment when construction begins in 2027, with energy service planned to start in late 2027. The map pin remains listed as announced.
Every step so far, and what comes next
-
DoneSeptember 30, 2026
Definitive agreements take effect
Black Hills said definitive agreements to serve the planned Cheyenne data center became effective September 30, 2026, with terms through 2048.
-
DoneOctober 6, 2026
Company announces the $1.8 billion generation plan
Black Hills announced plans to invest $1.8 billion between 2027 and 2029 in 564 megawatts of company-owned generation at Cheyenne Prairie Generating Station, the figure used on the map.
-
Next2027
Generation construction expected to begin
The official release expects construction of the company-owned generation to begin in 2027, with energy service planned to start in late 2027. The map pin remains listed as announced.
Worth knowing
- The $1.8 billion figure is official company-owned generation capital from 2027 to 2029 for 564 megawatts at Cheyenne Prairie Generating Station. It does not include the 2.1 gigawatts of third-party resources, the remaining 26 megawatts of market and retail supply used to reach 590 megawatts of grid-connected service, or anticipated additional transmission investment.
- Expected net income, unlevered free cash flow, and Google's $399 million refundable advances are financial or financing figures, not replacements for the map investment total.
- The $1.8 billion is Black Hills' generation investment to serve a planned Google data center, not Google's own campus investment. The map pin remains listed as announced, and this page does not change any map stage field.
Go deeper
Last checked Nov 23, 2026. We add a step when it happens and link the source.
Tracking saves to this device only. No account, no email, free.