BNA New Horizon airport program
A roughly $2.96 billion airside and landside program at Nashville International Airport, with the Concourse D extension already open and several other projects under construction.
Show on the map: BNA New Horizon airport program
- InvestmentThe airport authority's investor page, reviewed on November 23, 2026, puts the total estimated cost of New Horizon at approximately $2.96 billion, the figure used on the map. That total is divided into New Horizon I airside projects at about $1.62 billion and New Horizon II landside projects at about $1.34 billionMetropolitan Nashville Airport Authority, Nov 23, 2026
- Concourse D extensionNew Horizon I includes the Concourse D Extension, which opened on July 8, 2025 and expanded Concourse D from 6 gates to 11 gatesMetropolitan Nashville Airport Authority, Nov 23, 2026
- Work now underway or in planningAs of the investor page reviewed on November 23, 2026, demolition of the existing Concourse A is in progress ahead of reconstructing a new 374,000 square foot Concourse A with 16 gates and added ticket counters. Initial phases of baggage-handling improvements and the Central Ramp expansion are in progress. On the landside, roadway projects and a new surface parking lot for employee parking and valet overflow are in progress, while a new consolidated rental car facility and a new parking garage are in the planning stageMetropolitan Nashville Airport Authority, Nov 23, 2026
Next gate
Concourse A reconstruction continues
Demolition of the existing Concourse A is currently in progress
The airport authority's investor page says demolition of the existing Concourse A is currently in progress, to be followed by a new 374,000 square foot concourse with 16 gates. That page does not give a single program-wide completion date.
Every step so far, and what comes next
-
DoneJuly 8, 2025
Concourse D extension opened
The Concourse D Extension opened on July 8, 2025, expanding Concourse D from 6 gates to 11 gates.
Source: Metropolitan Nashville Airport Authority, Nov 23, 2026
-
NextAs of the investor page reviewed November 23, 2026
Concourse A reconstruction and other in-progress work continue
Demolition of the existing Concourse A is in progress, along with baggage-handling, Central Ramp, roadway, and surface-parking work. The consolidated rental car facility and a new parking garage remain in the planning stage.
Source: Metropolitan Nashville Airport Authority, Nov 23, 2026
Worth knowing
- The investor page used as the official source does not show a publish date; it was reviewed on November 23, 2026.
- That page does not state a single completion year for the whole New Horizon program, so none is used here. Individual project statuses (in progress, planning, or already open) are taken from that official page.
- New Horizon I and II subtotals are part of the same approximately $2.96 billion program, not additional to the map figure.
Go deeper
Last checked Nov 23, 2026. We add a step when it happens and link the source.