Track your favorite projects · Manufacturing
Boeing advanced combat aircraft facility, St. Louis
A $1.8 billion St. Louis County expansion under construction for advanced aircraft assembly, with official 2023 state and company statements of more than 500 new jobs and later confirmation that site construction is underway in phases through 2030.
Show on the map: Boeing advanced combat aircraft facility, St. Louis
- InvestmentThe Missouri Department of Economic Development said on November 6, 2023, that Boeing's expansion in St. Louis County would include a $1.8 billion investment and the creation of more than 500 new jobs, the figure used on the map. In the same official release, Boeing Air Dominance vice president Steve Nordlund said the company was expanding both its team and the state-of-the-art technology as it built toward the future of advanced manufacturing in Missouri.Missouri Department of Economic Development, Nov 6, 2023
- Scope and construction statusA June 5, 2025 official Jacobs release says Jacobs was selected to deliver design, engineering, and environmental services for Boeing's multi-billion expansion at its St. Louis campus. That later official release describes a 1.1 million square foot expansion designed to nearly double Boeing's regional manufacturing footprint, with advanced assembly facilities and an associated post-assembly operations center for future generations of advanced aircraft. It says site construction is underway and will be completed in multiple phases between 2026 and 2030. The later official release does not restate the $1.8 billion figure and is not used to replace the map total.Jacobs, Jun 5, 2025
Next gate
Phased completion of the site expansion
Between 2026 and 2030, according to the June 5, 2025 official Jacobs release
Official contractor materials say site construction is underway and will be completed in multiple phases between 2026 and 2030. This pass did not find a later official completion date for the full expansion.
Every step so far, and what comes next
-
DoneNovember 6, 2023
Missouri announces a $1.8 billion Boeing expansion
The official state release said the St. Louis County expansion would include a $1.8 billion investment, the figure used on the map, and more than 500 new jobs. Boeing said it was expanding in Missouri.
Source: Missouri Department of Economic Development, Nov 6, 2023
-
DoneJune 5, 2025
Contractor says site construction is underway
Jacobs said it was selected for Boeing's St. Louis campus expansion, described a 1.1 million square foot project, and said site construction was underway, to be completed in phases between 2026 and 2030.
Source: Jacobs, Jun 5, 2025
-
NextBetween 2026 and 2030
Phased completion of the site expansion
The official June 5, 2025 contractor release says the expansion will be completed in multiple phases between 2026 and 2030.
Source: Jacobs, Jun 5, 2025
Worth knowing
- The map figure is the official $1.8 billion investment stated in the November 6, 2023 Missouri release. The June 5, 2025 Jacobs release describes a multi-billion expansion and does not restate the $1.8 billion figure; that later wording is not used to replace the map total.
- The 2023 official release discussed St. Louis County as the location under consideration, while also quoting Boeing as expanding in Missouri. Later official Jacobs materials, including a quote from Boeing St. Louis site leadership, confirm a St. Louis campus expansion with construction underway.
- This page does not add unsourced program names or aircraft designations that were not stated in the official materials reviewed.
Last checked Nov 23, 2026. We add a step when it happens and link the source.