Brent Spence Bridge Corridor Project, Phase I
A $4.05 billion first phase for a new cable-stayed companion bridge and rebuilt approaches, with official groundbreaking in May 2026 and no tolls.
Show on the map: Brent Spence Bridge Corridor Project, Phase I
- Investment$4.05 billion for this first phase, the figure used on the map. A March 16, 2026 Kentucky Transportation Cabinet release said that construction cost had been verified by two independent estimators and that Kentucky's share is $1.7 billion. Official groundbreaking materials say the project is partially funded by two federal grants totaling $1.63 billion, with the balance expected from KYTC and ODOT state revenues and/or financing, and with no tollsKentucky Transportation Cabinet, Mar 16, 2026
- ScopeA new cable-stayed companion bridge immediately west of the existing Brent Spence Bridge, plus rebuilt approaches. The existing 1963 bridge is to carry local traffic, with interstate traffic moving to the companion bridge. Official May 8, 2026 groundbreaking materials also describe overhauled connections, including more than 30 overpasses and underpasses in Ohio and a dozen in Kentucky, plus pedestrian and bicycle pathsOffice of the Governor of Ohio, May 8, 2026
- GroundbreakingGovernors Mike DeWine and Andy Beshear marked the official launch and groundbreaking on May 8, 2026. Early work that spring and summer was to include approach work, utility relocations, and preparation for bridge foundation work in the Ohio RiverOffice of the Governor of Ohio, May 8, 2026
- ScheduleThe companion bridge is expected to open in 2031, with approach work substantially complete by 2033Office of the Governor of Ohio, May 8, 2026
Next gate
Companion bridge expected to open
2031, with approach work substantially complete by 2033
Official May 8, 2026 groundbreaking materials say the companion bridge is expected to open in 2031, with approach work substantially complete by 2033. A timeline and cost for later phases of the 8-mile corridor, including rehabilitation of the existing Brent Spence Bridge, will be estimated closer to construction.
Every step so far, and what comes next
-
DoneMarch 16, 2026
Kentucky announces $4.05 billion Phase I and a spring groundbreaking
Governor Beshear and KYTC said construction of the first portion would cost $4.05 billion, with Kentucky's share $1.7 billion, and that a groundbreaking was planned for spring.
-
DoneMay 8, 2026
Official groundbreaking
Governors DeWine and Beshear broke ground on Phase I and said early construction would include approach work, utility relocations, and preparation for in-river foundation work.
-
Next2031
Companion bridge expected to open
The opening year given in the official groundbreaking materials, with approach work substantially complete by 2033.
Worth knowing
- The $4.05 billion figure is the official Phase I construction cost, not a published total for later corridor phases.
- The project spans Kentucky and Ohio. The map pin is listed in Kentucky.
- The 2031 and 2033 dates are official targets and may move.
Go deeper
Last checked Nov 23, 2026. We add a step when it happens and link the source.