Brent Spence Bridge Corridor Project, Phase I

Kentucky Transportation Cabinet and Ohio Department of Transportation · Over the Ohio River between Covington, Kentucky, and Cincinnati, Ohio, immediately west of the existing 1963 Brent Spence Bridge

Under construction

A $4.05 billion first phase for a new cable-stayed companion bridge and rebuilt approaches, with official groundbreaking in May 2026 and no tolls.

Show on the map: Brent Spence Bridge Corridor Project, Phase I

Next gate

Companion bridge expected to open

2031, with approach work substantially complete by 2033

Official May 8, 2026 groundbreaking materials say the companion bridge is expected to open in 2031, with approach work substantially complete by 2033. A timeline and cost for later phases of the 8-mile corridor, including rehabilitation of the existing Brent Spence Bridge, will be estimated closer to construction.

Every step so far, and what comes next

  1. DoneMarch 16, 2026

    Kentucky announces $4.05 billion Phase I and a spring groundbreaking

    Governor Beshear and KYTC said construction of the first portion would cost $4.05 billion, with Kentucky's share $1.7 billion, and that a groundbreaking was planned for spring.

  2. DoneMay 8, 2026

    Official groundbreaking

    Governors DeWine and Beshear broke ground on Phase I and said early construction would include approach work, utility relocations, and preparation for in-river foundation work.

  3. Next2031

    Companion bridge expected to open

    The opening year given in the official groundbreaking materials, with approach work substantially complete by 2033.

Worth knowing

Go deeper

Last checked Nov 23, 2026. We add a step when it happens and link the source.

Tracking saves to this device only. No account, no email, free.