California High Speed Rail, Central Valley construction

California High Speed Rail Authority · Merced to Bakersfield, California (pin at Fresno)

Under construction

The 119-mile Merced to Bakersfield construction segment, with 92 guideway miles complete as of August 2026.

Show on the map: California High Speed Rail, Central Valley construction

Next gate

Construction Package 1 contract completion

Forecast for December 2026

The October 2026 status report, with data through August 31, lists a current forecast contract completion date of December 2026 for Construction Package 1.

Every step so far, and what comes next

  1. DoneAugust 2025

    Package 4 contract completed

    The October 2026 report says Construction Package 4 achieved substantial completion in January 2024 and final contract completion in August 2025.

  2. DoneAugust 2026

    92 guideway miles complete

    Two more guideway miles and four structures were finished in August 2026, bringing the segment to 92 complete guideway miles.

  3. NextDecember 2026 (forecast)

    Package 1 contract completion

    The report's current forecast contract completion date for Construction Package 1.

Worth knowing

Last checked Nov 23, 2026. We add a step when it happens and link the source.