Cayuga Energy Complex combined-cycle units

Duke Energy Indiana · Cayuga Generating Station, Vermillion County, Indiana

Under construction, first unit due 2029

Two new gas-fired combined-cycle units, about 738 megawatts each, at an existing Indiana power plant site.

Show on the map: Cayuga gas plant

Next gate

First unit in service

By Sept 1, 2029 (order condition)

The first unit is due in service by Sept 1, 2029 and the second by May 29, 2030.

Every step so far, and what comes next

  1. DoneOct 29, 2025

    Indiana regulators approve the certificate and cost estimate

    The Indiana Utility Regulatory Commission approved the certificate and a best estimate of construction costs of about $3.3 billion.

  2. DoneMay 14, 2026

    Duke Energy breaks ground

    Duke Energy held a ceremonial groundbreaking for two combined cycle natural gas units at the Cayuga Generating Station in Vermillion County.

  3. NextBy Sept 1, 2029 (order condition)

    First unit in service

    The first unit is due in service by Sept 1, 2029 and the second by May 29, 2030.

  4. ExpectedBy May 29, 2030

    Second unit in service

    The second unit is due in service by May 29, 2030.

Worth knowing

Last checked Nov 28, 2026. We add a step when it happens and link the source.