Chesterfield Energy Reliability Center
A November 25, 2025 Virginia State Corporation Commission final order granted Dominion Energy Virginia a certificate to construct and operate the approximately 944 megawatt Chesterfield Energy Reliability Center, using a $1.47 billion cost estimate.
Show on the map: Chesterfield Energy Reliability Center
- Official cost and certificateThe official November 25, 2025 Virginia State Corporation Commission Final Order in Case No. PUR-2025-00037 grants Virginia Electric and Power Company, doing business as Dominion Energy Virginia, a certificate of public convenience and necessity to construct and operate the Chesterfield Energy Reliability Center. The official order recites that, as estimated by the Company, the total projected cost of the Project is $1.47 billion, excluding financing costs, the figure used on the map. In its ordering paragraphs, the Commission directs that, to the extent project costs exceed or are expected to exceed the $1.47 billion cost estimate, Dominion shall provide testimony and supporting cost details as part of the initial application for recovery of those costs. The Commission issued Certificate No. EG-DEV-CHE-2025-A authorizing construction and operation of an approximately 944 megawatt nominal flexible fuel electric generating facility in Chesterfield County, located within the footprint of a recently retired coal unit (Unit 6) at the company's existing Chesterfield Power Station site.Virginia State Corporation Commission, Nov 25, 2025
- Facility and schedule in the official orderThe official order recites that the facility would comprise four natural gas-fired General Electric 7-F combustion turbines, and that Dominion projected the CERC could be commercially operational by June 1, 2029. The order also refers to that date as the projected in-service date of June 1, 2029.Virginia State Corporation Commission, Nov 25, 2025
- Rate adjustment not addedThe same official order approves a rate adjustment clause, designated Rider CERC, with a rate-year revenue requirement of $35,739,807, effective for usage on and after January 1, 2026. That official revenue-requirement figure is rate recovery and is not used to replace the $1.47 billion project cost estimate.Virginia State Corporation Commission, Nov 25, 2025
Next gate
Official order grants a certificate and recites a projected in-service date of June 1, 2029
After the official November 25, 2025 Final Order
The official Final Order granted the certificate and recited a projected in-service date of June 1, 2029. This pass did not find an official construction-start confirmation in that order. The map pin remains listed as under construction.
Every step so far, and what comes next
-
DoneMarch 3, 2025
Dominion files for a certificate and a rate adjustment clause
The official Final Order recites that Dominion filed its application on March 3, 2025, for a certificate to construct and operate the approximately 944 megawatt Chesterfield Energy Reliability Center and for approval of Rider CERC, with a total projected cost of $1.47 billion, excluding financing costs.
-
DoneNovember 25, 2025
Virginia SCC grants the certificate and approves Rider CERC
The official Final Order granted Certificate No. EG-DEV-CHE-2025-A to construct and operate the facility, used the $1.47 billion cost estimate, the figure used on the map, approved Rider CERC, and recited a projected in-service date of June 1, 2029.
-
NextAfter the official November 25, 2025 Final Order
Official order grants a certificate and recites a projected in-service date of June 1, 2029
The official Final Order granted the certificate and recited a projected in-service date of June 1, 2029. This pass did not find an official construction-start confirmation in that order. The map pin remains listed as under construction.
Worth knowing
- The map figure is the official $1.47 billion total projected cost recited in the November 25, 2025 Final Order, which the order also identifies as a cost estimate excluding financing costs. This page does not change any map usd field.
- The official Rider CERC rate-year revenue requirement of $35,739,807 is rate recovery and is not used to replace the $1.47 billion project cost estimate.
- The official Final Order grants a certificate to construct and operate the facility and recites a projected in-service date of June 1, 2029. This pass did not find an official construction-start confirmation in that order. The map pin remains listed as under construction, and this page does not change any map stage field.