Colorado's Power Pathway transmission
A $1.7 billion, roughly 550 mile, 345-kilovolt transmission project across eastern Colorado, with segments 1 through 3 in service and segments 4 and 5 expected to be completed in 2026 and 2027.
Show on the map: Colorado's Power Pathway transmission
- Investment and scopeXcel Energy's official Colorado's Power Pathway project-description page, retrieved November 24, 2026, describes the project as a $1.7 billion investment, the figure used on the map, to improve the state's electric grid and enable future renewable energy development. It says the system will span twelve counties, primarily in eastern Colorado, and include approximately 550 miles of new double-circuit transmission line, four new substations, and equipment additions or expansion of four existing substations. The official page says the project's proposed 345-kilovolt system will connect eastern Colorado to the Front Range and will carry the approximately 5,500 megawatts of new wind, solar, and other resources Xcel Energy plans to add through 2030.Xcel Energy, Colorado's Power Pathway, Nov 24, 2026
- Status and remaining segmentsThe same official page says segments 1, 2, and 3, including the Canal Crossing, Goose Creek, and May Valley substations, are constructed and in service, and that the other segments are expected to be completed in 2026 and 2027. Segment tables on the page list segment 4, May Valley to Sandstone to Tundra, and segment 5, Sandstone to Harvest Mile, with in-service dates in 2027. The Colorado Public Utilities Commission issued written approval of all five segments on June 2, 2022. The official page also says the Commission did not approve the May Valley-Longhorn Extension in a January 2024 Phase II decision, and that further development of that extension has been paused and is not part of the continuing five-segment project.Xcel Energy, Colorado's Power Pathway, Nov 24, 2026
Next gate
Segments 4 and 5 expected in service
2027, according to the official project-description page retrieved November 24, 2026
The official project page says the remaining segments are expected to be completed in 2026 and 2027, and the segment tables list 2027 in-service dates for segments 4 and 5. Segments 1 through 3 are already in service.
Every step so far, and what comes next
-
DoneJune 2, 2022
Colorado Public Utilities Commission approves the five-segment project
The official project page says state regulators issued a final written decision on June 2, 2022, giving Xcel Energy authority to move forward with all five segments.
-
DoneAs of the official project page retrieved November 24, 2026
Segments 1, 2, and 3 are in service
The official page says segments 1, 2, and 3, including the Canal Crossing, Goose Creek, and May Valley substations, are constructed and in service.
-
Next2027, according to the official segment tables
Segments 4 and 5 expected in service
The official page expects the remaining segments to be completed in 2026 and 2027, and lists 2027 in-service dates for segments 4 and 5.
Worth knowing
- The official $1.7 billion figure is for the five-segment Power Pathway project. The May Valley-Longhorn Extension was not approved and is not added to this pin.
- The official project page is a living page and is dated by retrieval on November 24, 2026.
- The pin location is approximate, near Limon in the middle of the loop. The project is partly in service. The map pin remains listed as under construction, and this page does not change any map stage field.
Go deeper
Last checked Nov 24, 2026. We add a step when it happens and link the source.