Crane Clean Energy Center restart (Three Mile Island Unit 1)
A restart of the 835 megawatt former Three Mile Island Unit 1 reactor, with an official company estimate of approximately $1.6 billion in capital spending, a 20-year Microsoft power purchase agreement, and a $1 billion DOE loan closed in November 2025.
Show on the map: Crane Clean Energy Center restart (Three Mile Island Unit 1)
- Investment and power agreementConstellation's official third-quarter 2024 results, dated November 4, 2024, say that during the quarter the company executed a 20-year power purchase agreement with Microsoft that will support the restart of Three Mile Island Unit 1, renamed the Crane Clean Energy Center, which was retired in 2019. The official results estimate that the project will require approximately $1.6 billion of cash from operations for capital expenditures necessary to restart the plant, the figure used on the map, with an estimated in-service date of 2028. They also say the restart and delivery of electricity under the agreement are subject to regulatory approvals, including an NRC safety and environmental review.Constellation Energy, Nov 4, 2024
- DOE loan and site activityAn official November 18, 2025 Constellation release says the Crane Clean Energy Center is backed by a $1 billion U.S. Department of Energy loan and describes the plant as adding 835 megawatts. The official Department of Energy Crane Restart page, last updated October 14, 2026, confirms that in November 2025 the department closed a $1 billion loan to Constellation Energy Generation to help finance the restart of the 835 megawatt reactor, subject to NRC licensing approvals. That official loan is financing support and is not used to replace the company's approximately $1.6 billion capital-spending estimate. The official November 18, 2025 company release also says the center is more than 80 percent staffed with over 500 employees and that inspections of key plant components and regulatory reviews continue on schedule.Constellation Energy, Nov 18, 2025
Next gate
Restart remains subject to NRC approvals, with an official 2028 in-service estimate
Estimated in-service date of 2028, according to the official November 4, 2024 results
The official 2024 results estimated an in-service date of 2028, subject to NRC and other approvals. The official November 18, 2025 release and the official DOE page confirm a closed $1 billion loan and continuing inspections and staffing. This pass did not find a later official change to that 2028 estimate in the materials reviewed.
Every step so far, and what comes next
-
DoneNovember 4, 2024
Company estimates approximately $1.6 billion to restart the plant
Constellation's official third-quarter 2024 results announced a 20-year Microsoft power purchase agreement supporting the Crane restart and estimated approximately $1.6 billion of capital spending, the figure used on the map, with an estimated in-service date of 2028.
-
DoneNovember 18, 2025
DOE loan closes and the company reports site activity underway
The official company release said a $1 billion DOE loan was backing the 835 megawatt restart, and that the site was more than 80 percent staffed with inspections continuing. The official DOE page later confirmed the November 2025 loan close.
-
Next2028, according to the official November 4, 2024 estimate
Estimated in-service date, subject to NRC and other approvals
The official 2024 results estimated an in-service date of 2028, subject to regulatory approvals.
Worth knowing
- The map figure is the official company estimate of approximately $1.6 billion of capital spending in the November 4, 2024 results. The official $1 billion DOE loan closed in November 2025 is financing support and is not used to replace that estimate.
- Economic-impact figures cited in later official company materials, including jobs and state GDP estimates from a commissioned study, are not added to the map total.
- The official 2024 results give an estimated in-service date of 2028, subject to regulatory approvals. The map pin remains listed as under construction, and this page does not change any map stage field.