Track your favorite projects · AI data centers
Creekstone Gigasite
An AI data center campus near Delta with its own gas, solar and storage power, off the constrained grid.
Show on the map: Creekstone Gigasite
- Investment$17,082,408,000 over 20 years, per the state incentive agreementUtah Governor's Office of Economic Opportunity, Apr 9, 2026
- Jobs106 new jobsUtah Governor's Office of Economic Opportunity, Apr 9, 2026
- Site1,143 acres owned outright, near the Intermountain Power ProjectBusiness Wire, Jul 23, 2026
- First power blockAbout 220 MW from firm Kern River gas capacity; the campus is planned to scale past 10 GWBusiness Wire, Jul 23, 2026
Next gate
On-site power
2027
Creekstone plans to start generating power on site in 2027.
Every step so far, and what comes next
-
DoneJun 5, 2025
Heavy industrial zoning
Millard County approved heavy industrial zoning for the site.
Source: Creekstone Energy, Nov 23, 2026
-
DoneJul 1, 2025
Conditional use permit
Approved for a data center and on-site power generation.
Source: Creekstone Energy, Nov 23, 2026
-
DoneSep 2025
Gas interconnect agreement
Creekstone signed the interconnect agreement with Kern River.
Source: Creekstone Energy, Nov 23, 2026
-
DoneDec 29, 2025
Storage installed
Torus battery and flywheel equipment was installed on site.
Source: Creekstone Energy, Nov 23, 2026
-
DoneApr 9, 2026
State tax incentive
Utah awarded a post-performance tax credit tied to the $17 billion plan.
Source: Utah Governor's Office of Economic Opportunity, Apr 9, 2026
-
DoneJul 15, 2026
Gas metering building done
Construction of the natural gas metering building was completed.
Source: Creekstone Energy, Jul 15, 2026
-
DoneJul 23, 2026
Firm gas secured
43,000 dekatherms a day of firm Kern River capacity, enough for about 220 MW.
Source: Business Wire, Jul 23, 2026
-
Next2027
Power on site
Company target for first on-site generation.
Source: Business Wire, Jul 23, 2026
Worth knowing
- The $17 billion is spread over 20 years.
- The 10 GW goal is a long-term plan; the contracted gas covers the first block of about 220 MW.
- Air permits for the generation were still in final modeling per the company.
Last checked Nov 23, 2026. We add a step when it happens and link the source.