Track your favorite projects · AI data centers

Creekstone Gigasite

Creekstone Energy · Near Delta, Millard County, Utah

Under construction, gas hookup and power first

An AI data center campus near Delta with its own gas, solar and storage power, off the constrained grid.

Show on the map: Creekstone Gigasite

Next gate

On-site power

2027

Creekstone plans to start generating power on site in 2027.

Every step so far, and what comes next

  1. DoneJun 5, 2025

    Heavy industrial zoning

    Millard County approved heavy industrial zoning for the site.

  2. DoneJul 1, 2025

    Conditional use permit

    Approved for a data center and on-site power generation.

  3. DoneSep 2025

    Gas interconnect agreement

    Creekstone signed the interconnect agreement with Kern River.

  4. DoneDec 29, 2025

    Storage installed

    Torus battery and flywheel equipment was installed on site.

  5. DoneApr 9, 2026

    State tax incentive

    Utah awarded a post-performance tax credit tied to the $17 billion plan.

  6. DoneJul 15, 2026

    Gas metering building done

    Construction of the natural gas metering building was completed.

  7. DoneJul 23, 2026

    Firm gas secured

    43,000 dekatherms a day of firm Kern River capacity, enough for about 220 MW.

  8. Next2027

    Power on site

    Company target for first on-site generation.

Worth knowing

Last checked Nov 23, 2026. We add a step when it happens and link the source.

Tracking saves to this device only. No account, no email, free.