CTA Red Line Extension
A 5.5-mile extension of the Red Line south to 130th Street, with four new accessible stations, now under construction.
Show on the map: CTA Red Line Extension
- Investment$5.7 billion, the figure used on the map. A January 10, 2025 Full Funding Grant Agreement locked in $1.9 billion in federal funds, which CTA called the largest transit infrastructure grant in its history and the final piece of project fundingChicago Transit Authority, Jan 10, 2025
- ScopeA 5.5-mile extension from 95th Street to the vicinity of 130th Street, with four new accessible stations near 103rd Street, 111th Street, Michigan Avenue (near 116th), and 130th Street, plus a new rail yard and related facilities near 120th StreetChicago Transit Authority, Apr 24, 2026
- ContractorCTA awarded a design-build contract in August 2024 to Walsh-VINCI Transit Community PartnersChicago Transit Authority, Jan 10, 2025
- ScheduleCTA broke ground on April 24, 2026, at the future Michigan Avenue station. Station construction is to begin in 2027. The extension and stations are expected to be completed and in service in 2030Chicago Transit Authority, Apr 24, 2026
Next gate
Station construction begins
2027
CTA's April 24, 2026 groundbreaking release said construction was beginning in spring 2026, with drilling and foundations for new elevated-track columns, and that station construction would begin in 2027.
Every step so far, and what comes next
-
DoneJanuary 10, 2025
Federal full funding agreement signed
CTA and the Federal Transit Administration signed a $1.9 billion Full Funding Grant Agreement, completing funding for the $5.7 billion project.
-
DoneApril 24, 2026
Groundbreaking at the future Michigan Avenue station
Mayor Johnson and CTA officials broke ground on the extension. CTA said the line and stations are expected to be in service in 2030.
-
Next2027
Station construction begins
The date given in the April 2026 groundbreaking release.
-
Expected2030
Extension in service
CTA's published target for completing the extension and stations and placing them in service.
Worth knowing
- CTA's official releases describe a 5.5-mile extension. The map summary used 5.6 miles. This page uses the official 5.5-mile figure.
- The 2030 in-service date is CTA's published target and may move.
- Some speakers have cited a $1.973 billion federal figure. CTA's own funding announcement uses $1.9 billion for the Full Funding Grant Agreement.
Last checked Nov 23, 2026. We add a step when it happens and link the source.