Metro D Line Extension Section 3, Century City to Westwood

Los Angeles County Metropolitan Transportation Authority · Wilshire Boulevard corridor from Century City to Westwood, Los Angeles, California

Under construction

The final 2.56-mile subway segment of the D Line extension, from Century City to Westwood/UCLA and the Westwood/VA Hospital station, with operations forecast for fall 2027.

Show on the map: Metro D Line Extension Section 3, Century City to Westwood

Next gate

Revenue service forecast for fall 2027

Fall 2027, per Metro's November 18, 2026 community meeting materials, subject to change

Official Metro materials forecast Section 3 operations in fall 2027, with the stations contract scheduled for substantial completion on June 4, 2027.

Every step so far, and what comes next

  1. DoneMay 24, 2021

    Section 3 groundbreaking

    Metro held a groundbreaking ceremony at the West Los Angeles VA Medical Center to start Section 3 construction.

  2. DoneDecember 23, 2025

    Tunnels contract reached substantial completion

    The July 2026 status report said Contract C1151 attained contractual substantial completion on December 23, 2025.

  3. DoneJuly 2026

    Project reported at 86% complete

    Metro's July 2026 status report said the project had achieved 86% completion based on earned value, with the current budget still $3.7 billion.

  4. ExpectedJune 4, 2027

    Stations contract scheduled for substantial completion

    The date given in the July 2026 status report for Contract C1152.

  5. NextFall 2027

    Operations forecast to begin

    The operations window given in Metro's November 18, 2026 community meeting materials, marked subject to change.

Worth knowing

Last checked Nov 23, 2026. We add a step when it happens and link the source.