Track your favorite projects · Infrastructure
Metro D Line Extension Section 3, Century City to Westwood
The final 2.56-mile subway segment of the D Line extension, from Century City to Westwood/UCLA and the Westwood/VA Hospital station, with operations forecast for fall 2027.
Show on the map: Metro D Line Extension Section 3, Century City to Westwood
- Investment$3.7 billion, the figure used on the map. Metro's July 2026 status report said the current budget and current forecast were unchanged at $3.7 billion, and that the Life of Project budget is $3.2 billion excluding $387.4 million in finance chargesLos Angeles County Metropolitan Transportation Authority, Jul 2026
- ScopeA 2.56-mile underground extension from the future Century City station to two new stations, Westwood/UCLA and Westwood/VA Hospital, as stated in Metro's November 18, 2026 community meeting materialsLos Angeles County Metropolitan Transportation Authority, Nov 18, 2026
- ProgressThe July 2026 status report said the project had reached 86% completion based on earned value. Contract C1151, the tunnels contract, reached contractual substantial completion on December 23, 2025. Contract C1152, covering stations, trackwork, systems, and testing, had a substantial completion date of June 4, 2027Los Angeles County Metropolitan Transportation Authority, Jul 2026
- ScheduleMetro's November 18, 2026 community meeting listed Section 3 construction from 2019 through 2027 and operations in fall 2027, with those dates marked subject to change. The official project page also records a May 24, 2021 groundbreaking at the West Los Angeles VA Medical CenterLos Angeles County Metropolitan Transportation Authority, Nov 18, 2026
Next gate
Revenue service forecast for fall 2027
Fall 2027, per Metro's November 18, 2026 community meeting materials, subject to change
Official Metro materials forecast Section 3 operations in fall 2027, with the stations contract scheduled for substantial completion on June 4, 2027.
Every step so far, and what comes next
-
DoneMay 24, 2021
Section 3 groundbreaking
Metro held a groundbreaking ceremony at the West Los Angeles VA Medical Center to start Section 3 construction.
Source: Los Angeles County Metropolitan Transportation Authority, Nov 23, 2026
-
DoneDecember 23, 2025
Tunnels contract reached substantial completion
The July 2026 status report said Contract C1151 attained contractual substantial completion on December 23, 2025.
Source: Los Angeles County Metropolitan Transportation Authority, Jul 2026
-
DoneJuly 2026
Project reported at 86% complete
Metro's July 2026 status report said the project had achieved 86% completion based on earned value, with the current budget still $3.7 billion.
Source: Los Angeles County Metropolitan Transportation Authority, Jul 2026
-
ExpectedJune 4, 2027
Stations contract scheduled for substantial completion
The date given in the July 2026 status report for Contract C1152.
Source: Los Angeles County Metropolitan Transportation Authority, Jul 2026
-
NextFall 2027
Operations forecast to begin
The operations window given in Metro's November 18, 2026 community meeting materials, marked subject to change.
Source: Los Angeles County Metropolitan Transportation Authority, Nov 18, 2026
Worth knowing
- The $3.7 billion current budget includes finance charges. The Life of Project budget cited in the July 2026 report is $3.2 billion excluding $387.4 million in finance charges.
- The fall 2027 operations date is from Metro's November 18, 2026 meeting materials and is marked subject to change. The July 2026 status report listed a forecast revenue service date of 2027 and an FFGA revenue service date of 2028.
- This page covers Section 3 only. Section 1 opened on May 8, 2026. Section 2 is a separate project still under construction.
Last checked Nov 23, 2026. We add a step when it happens and link the source.