Denver International Airport Great Hall Completion Phase
The official DEN Great Hall Program page, retrieved November 24, 2026, describes a $1.3 billion Completion Phase that began in late 2022 and is expected to be complete by the end of 2027, with sections opening along the way.
Show on the map: Denver International Airport Great Hall Completion Phase
- Completion Phase cost and scheduleThe official Denver International Airport Great Hall Program page, retrieved November 24, 2026, states that this $1.3 billion Great Hall Completion phase began in late 2022 and is expected to be complete by the end of 2027 with sections opening along the way. The official $1.3 billion Completion Phase figure is the amount used on the map. The official page says the Great Hall Project consists of three phases, and that the first two phases were completed within the original $770 million budget. That official earlier-phase budget is not added into this pin.Denver International Airport, Nov 24, 2026
- Scope and work already openedThe official page says the Completion Phase, the third and final phase and currently underway, will complete the full build-out of the Jeppesen Terminal, including the East Security Checkpoint on Level 6, renovated airline check-in facilities, new meet-and-greet areas, and the Center for Equity and Excellence in Aviation. It says the East Security Checkpoint opened on August 5, 2025, and that the renovated terminal is intended to help the airport prepare for future growth, including an anticipated 100 million passengers.Denver International Airport, Nov 24, 2026
Next gate
Official program page, retrieved November 24, 2026, pointed to completion by the end of 2027
As of the November 24, 2026 retrieval of the official DEN program page
The official page said the $1.3 billion Completion Phase began in late 2022 and is expected to be complete by the end of 2027, with sections opening along the way. The map pin remains listed as under construction.
Every step so far, and what comes next
-
DoneLate 2022
Great Hall Completion Phase work begins
The official program page retrieved November 24, 2026, says the $1.3 billion Completion Phase, the figure used on the map, began in late 2022.
-
DoneAugust 5, 2025
East Security Checkpoint opens
The official program page says the East Security Checkpoint, part of the Completion Phase, opened on August 5, 2025.
-
NextAs of the November 24, 2026 retrieval of the official DEN program page
Official program page, retrieved November 24, 2026, pointed to completion by the end of 2027
The official page said the $1.3 billion Completion Phase began in late 2022 and is expected to be complete by the end of 2027, with sections opening along the way. The map pin remains listed as under construction.
Worth knowing
- The map figure is the official $1.3 billion Great Hall Completion Phase cost stated on the official program page retrieved November 24, 2026. This page counts the Completion Phase only. The official $770 million budget for the first two phases is not added. This page does not change any map usd field.
- The official program page is a living page and is dated here by retrieval on November 24, 2026.
- The official page states that the Completion Phase is underway. The map pin remains listed as under construction, and this page does not change any map stage field.
Go deeper
Last checked Nov 24, 2026. We add a step when it happens and link the source.