Destination CLT airport program
A $4 billion capital program whose terminal lobby is complete and whose $1 billion fourth parallel runway is still under construction, with opening planned in fall 2027.
Show on the map: Destination CLT airport program
- Investment$4 billion for the Destination CLT capital program as a whole, the figure used on the map, from official airport updates in 2024 and 2025Charlotte Douglas International Airport, Oct 1, 2024
- Terminal lobbyCLT announced on September 18, 2025, that the $608 million Terminal Lobby Expansion was complete. The project added 175,000 square feet of new space and renovated 191,000 square feet. Construction had started in December 2019Charlotte Douglas International Airport, Sep 18, 2025
- Fourth parallel runwayOfficial 2024 updates described the runway as a $1 billion project targeted for commissioning and opening in fall 2027. A January 26, 2026 airport update said the runway was approaching its halfway point, still with a scheduled opening in fall 2027Charlotte Douglas International Airport, Jan 26, 2026
- Other workThe January 2026 update also said Concourse E renovations are scheduled for completion in March 2027 and Concourse D work in late 2026. The September 2025 lobby-completion story said concourse renovations and a later phase of the Concourse A expansion were still aheadCharlotte Douglas International Airport, Jan 26, 2026
Next gate
Fourth parallel runway scheduled to open
Fall 2027
Official airport updates in 2024 and January 2026 keep the $1 billion fourth parallel runway on a fall 2027 commissioning and opening schedule.
Every step so far, and what comes next
-
DoneDecember 2019
Terminal lobby construction began
CLT later said construction on the Terminal Lobby Expansion started in December 2019.
Source: Charlotte Douglas International Airport, Sep 18, 2025
-
DoneSeptember 2025
Terminal lobby completed
CLT announced completion of the $608 million lobby expansion, the signature project in the $4 billion Destination CLT program.
Source: Charlotte Douglas International Airport, Sep 18, 2025
-
DoneJanuary 2026
Fourth runway approaching halfway
An official airport update said the fourth parallel runway was approaching its halfway point, with opening still scheduled for fall 2027.
Source: Charlotte Douglas International Airport, Jan 26, 2026
-
NextFall 2027
Fourth parallel runway scheduled to open
The commissioning and opening window given in official 2024 and 2026 airport updates.
Source: Charlotte Douglas International Airport, Jan 26, 2026
Worth knowing
- The $4 billion figure is the airport's official program total, covering multiple projects, not the cost of any single building or runway.
- The terminal lobby is complete. The program as a whole remains under construction because of the runway and concourse work.
- The fall 2027 runway opening is an official target and may move.
Last checked Nov 23, 2026. We add a step when it happens and link the source.