DFW Airport Terminal F
A new terminal, expanded to about $4 billion and 31 gates for American Airlines, with the first 15 gates still scheduled to open in 2027.
Show on the map: DFW Airport Terminal F
- InvestmentAbout $4 billion, the figure used on the map, after DFW and American Airlines announced on May 1, 2025, that they would expand Terminal F from a 15-gate plan to 31 gates served entirely by AmericanDallas Fort Worth International Airport, May 1, 2025
- GroundbreakingDFW broke ground on November 19, 2024, on what was then described as a $1.6 billion, 15-gate first-phase program anticipated to open in 2027Dallas Fort Worth International Airport, Nov 19, 2024
- First-phase scheduleThe May 1, 2025 expansion announcement said the original first phase was well underway and still scheduled to be operational in 2027, with newly added phases planned to come online later. A November 3, 2026 update repeated that the first phase is anticipated to open 15 gates in 2027Dallas Fort Worth International Airport, May 1, 2025
- ProgressOn November 3, 2026, DFW said all six prefabricated modules of the new Terminal F Skylink station had been lifted into place, with work continuing to connect them into the stationDallas Fort Worth International Airport, Nov 3, 2026
Next gate
First 15 gates anticipated to open
2027
Official DFW materials from 2025 and November 2026 still schedule the first phase, 15 gates, to open in 2027. Later phases that complete the 31-gate terminal do not have a single published opening year in those releases.
Every step so far, and what comes next
-
DoneNovember 19, 2024
Groundbreaking on the first phase
DFW broke ground on Terminal F as a 15-gate, $1.6 billion first-phase program anticipated to open in 2027.
Source: Dallas Fort Worth International Airport, Nov 19, 2024
-
DoneMay 1, 2025
Plan expanded to about $4 billion and 31 gates
DFW and American Airlines announced an expanded Terminal F, with American to occupy all 31 gates and the first phase still scheduled for 2027.
Source: Dallas Fort Worth International Airport, May 1, 2025
-
DoneNovember 3, 2026
Skylink station modules lifted into place
DFW said all six prefabricated Skylink station modules had been lifted onto the guideway.
Source: Dallas Fort Worth International Airport, Nov 3, 2026
-
Next2027
First 15 gates anticipated to open
The first-phase opening year given in official 2025 and 2026 DFW releases.
Source: Dallas Fort Worth International Airport, Nov 3, 2026
Worth knowing
- The official total is 'about $4 billion,' after the May 2025 expansion from the earlier $1.6 billion, 15-gate plan.
- The 2027 date is for the first 15 gates, not for the full 31-gate terminal.
- That 2027 target may still move.