Dinosaur-Longshore 765 kV Transmission Line
A permitted 242.56 mile, 765-kilovolt transmission line between Somervell and Howard counties, with an official total estimated cost of $2,242,769,000 after a Public Utility Commission of Texas order on August 28, 2026.
Show on the map: Dinosaur-Longshore 765 kV Transmission Line
- InvestmentThe Public Utility Commission of Texas's August 28, 2026 official order in Docket 59315 amends Oncor's certificate of convenience and necessity to include the Dinosaur switch-to-Longshore switch 765-kilovolt transmission facilities along route 559. Finding of fact 81 states that the total estimated cost to construct those facilities along route 559 is approximately $2,242,769,000, the figure used on the map. Findings 79 and 80 break that official total into an estimated construction cost for route 559 of $1,704,004,000, excluding station costs, and $538,765,000 of station work, including new 765-kilovolt switchyards at both Longshore switch and Dinosaur station.Public Utility Commission of Texas, Aug 28, 2026
- Scope and scheduleThe same official order describes a 765-kilovolt single-circuit line along route 559, which finding of fact 75 states is 242.56 miles in length, from a proposed Dinosaur switch about 3 miles north of Glen Rose in Somervell County, adjacent to existing 345-kilovolt circuits, to Oncor's Longshore switch about 4.5 miles west of Forsan in Howard County. The line also crosses Borden, Bosque, Brown, Callahan, Coke, Coleman, Comanche, Eastland, Erath, Glasscock, Hamilton, Hood, Jones, Mitchell, Nolan, Runnels, Shackelford, Stephens, Sterling, and Taylor counties. In the application, Oncor estimated it would acquire all rights-of-way by June 2027, complete construction by June 2029, and energize the facilities by June 2029, estimates premised on Commission approval within 180 days of filing.Public Utility Commission of Texas, Aug 28, 2026
Next gate
Right-of-way, construction, and energization on the application schedule
Rights-of-way estimated by June 2027 and energization by June 2029, according to the official August 28, 2026 order
The official order records Oncor's estimate that it would acquire all rights-of-way by June 2027 and energize the facilities by June 2029, premised on Commission approval within 180 days of filing. The project remains permitted. This pass did not find a later official construction-start confirmation.
Every step so far, and what comes next
-
DoneAugust 28, 2026
Commission approves route 559 and a $2,242,769,000 official cost
The Public Utility Commission of Texas amended Oncor's certificate to include the Dinosaur-to-Longshore 765-kilovolt facilities along route 559 and found a total estimated cost of approximately $2,242,769,000, the figure used on the map.
-
NextJune 2029, according to the estimate recorded in the official order
Energization targeted, if the application schedule holds
Oncor estimated it would complete construction and energize the facilities by June 2029, premised on timely Commission approval. The map pin remains listed as permitted.
Worth knowing
- The map figure is the official total estimated cost of approximately $2,242,769,000 along approved route 559. That official total includes $538,765,000 of station work at both Longshore switch and Dinosaur station.
- The sister Longshore-Drill Hole 765-kilovolt project, approved the same day in Docket 59029, also includes official station work at Longshore switch in its own total. The two official certificate totals should not be added together as if the shared Longshore switchyard were unique to each project.
- Oncor's June 2029 energization estimate was premised on Commission approval within 180 days of filing. The map pin remains listed as permitted, and this page does not change any map stage field.