Empire Wind 1 offshore wind farm

Equinor · Wind farm 15 to 30 miles off the New York coast, with the map pin at the South Brooklyn Marine Terminal in Brooklyn, the onshore port and grid connection

Under construction

An 810 megawatt offshore wind farm for New York, about 80% complete, with turbine installation and first power now aimed at 2027.

Show on the map: Empire Wind 1 offshore wind farm

Next gate

Turbine installation and first power

Installation expected to start in 2027, with first power in the first half of 2027

Equinor's October 28, 2026 third-quarter call said most of the remaining scope is offshore turbine installation, expected to start in 2027, with first power during the first half of 2027.

Every step so far, and what comes next

  1. DoneEnd of December 2024 / January 2, 2025

    Financial close

    Equinor announced that Empire Wind 1 had secured a project financing package of more than $3 billion and that expected total capital investment was about $5 billion, including terminal fees and expected tax credits.

  2. DoneSummer and early fall of 2025

    All 54 monopile foundations installed

    The official project site says monopiles were installed in that campaign and that all 54 foundations are in place.

  3. DoneJanuary 2026

    Offshore substation installed

    The official project site says the offshore substation was placed on its jacket in the lease area in January 2026.

  4. DoneOctober 28, 2026

    Project reported about 80% complete

    Equinor's third-quarter call said the project was around 80% complete, with turbine installation still ahead.

  5. NextFirst half of 2027

    Turbine installation and first power

    The dates given on the October 28, 2026 call for starting turbine installation and reaching first power.

Worth knowing

Last checked Nov 23, 2026. We add a step when it happens and link the source.