Empire Wind 1 offshore wind farm
An 810 megawatt offshore wind farm for New York, about 80% complete, with turbine installation and first power now aimed at 2027.
Show on the map: Empire Wind 1 offshore wind farm
- InvestmentApproximately $5 billion, the figure used on the map, including fees for use of the South Brooklyn Marine Terminal and the effect of expected future investment tax credits, from Equinor's January 2, 2025 financial-close releaseEquinor, Jan 2, 2025
- Capacity810 megawatts, intended to deliver power into the New York City grid at Sunset Park, Brooklyn, and to supply more than 500,000 New York homes, according to the official project siteEmpire Wind, Nov 23, 2026
- Financing and contractEquinor said a project financing package of more than $3 billion reached financial close at the end of December 2024. In June 2024 it executed a 25-year purchase agreement with the New York State Energy Research and Development Authority at a strike price of $155.00 per megawatt-hourEquinor, Jan 2, 2025
- Offshore progressThe official project site says onshore construction at the South Brooklyn Marine Terminal began in spring 2024, marine work resumed in spring 2025, all 54 monopile foundations have been installed, and the offshore substation was installed in January 2026Empire Wind, Nov 23, 2026
- ScheduleOn Equinor's October 28, 2026 third-quarter call, the chief financial officer said Empire Wind was around 80% complete, that most remaining work is offshore turbine installation expected to start in 2027, a bit later than planned, and that first power is expected in the first half of 2027, with no change to total capital spendingEquinor, Oct 28, 2026
Next gate
Turbine installation and first power
Installation expected to start in 2027, with first power in the first half of 2027
Equinor's October 28, 2026 third-quarter call said most of the remaining scope is offshore turbine installation, expected to start in 2027, with first power during the first half of 2027.
Every step so far, and what comes next
-
DoneEnd of December 2024 / January 2, 2025
Financial close
Equinor announced that Empire Wind 1 had secured a project financing package of more than $3 billion and that expected total capital investment was about $5 billion, including terminal fees and expected tax credits.
Source: Equinor, Jan 2, 2025
-
DoneSummer and early fall of 2025
All 54 monopile foundations installed
The official project site says monopiles were installed in that campaign and that all 54 foundations are in place.
Source: Empire Wind, Nov 23, 2026
-
DoneJanuary 2026
Offshore substation installed
The official project site says the offshore substation was placed on its jacket in the lease area in January 2026.
Source: Empire Wind, Nov 23, 2026
-
DoneOctober 28, 2026
Project reported about 80% complete
Equinor's third-quarter call said the project was around 80% complete, with turbine installation still ahead.
Source: Equinor, Oct 28, 2026
-
NextFirst half of 2027
Turbine installation and first power
The dates given on the October 28, 2026 call for starting turbine installation and reaching first power.
Source: Equinor, Oct 28, 2026
Worth knowing
- The approximately $5 billion figure includes South Brooklyn Marine Terminal fees and the effect of expected future tax credits, not only turbine and foundation construction.
- The map pin is onshore at the South Brooklyn Marine Terminal. The turbines are 15 to 30 miles offshore.
- The official project site still says the project is expected to be fully operational in 2027. The October 2026 Equinor call is more specific: first power in the first half of 2027, with turbine installation starting later than first planned.
- This page does not treat later unofficial vessel-delay reporting as a source. The official delay statement used here is Equinor's own October 28, 2026 call.
Last checked Nov 23, 2026. We add a step when it happens and link the source.