Track your favorite projects · Power
Entergy gas plants for Meta
Three combined-cycle gas plants approved to support Meta's Richland Parish data center, with construction underway on the two Richland Parish units and the third scheduled for 2029.
Show on the map: Entergy gas plants for Meta
- Approval and scopeOn August 20, 2025, Entergy said the Louisiana Public Service Commission had approved an agreement allowing Entergy Louisiana to construct three new combined-cycle combustion turbine generation facilities to support Meta's data center in Richland Parish, plus new transmission facilities. Two plants are in Richland Parish, expected online in late 2028. The third is at Entergy's existing Waterford site in St. Charles Parish, expected to be operational by the end of 2029Entergy, Aug 20, 2025
- ConstructionEntergy's 2025 Performance Report said the company began construction in December 2025 on two new combined-cycle combustion turbine facilities in Richland Parish, called Franklin Farms 1 and Franklin Farms 2, and that it is also building Waterford 5, another combined-cycle plant, in Killona, projected to come online in 2029Entergy, Mar 2026
- Who paysThe August 20, 2025 release said Meta is paying its share of the costs for the infrastructure needed to support its operations, so that other customers are protected from those expensesEntergy, Aug 20, 2025
Next gate
Richland Parish plants expected online
Late 2028
Entergy's August 20, 2025 approval release said the two Richland Parish facilities are expected to come online in late 2028, with the Waterford plant expected by the end of 2029.
Every step so far, and what comes next
-
DoneAugust 20, 2025
LPSC approval for three combined-cycle plants
Entergy said the Louisiana Public Service Commission approved the agreement for three plants and related transmission to support Meta's Richland Parish data center.
Source: Entergy, Aug 20, 2025
-
DoneDecember 2025
Construction began on the two Richland Parish plants
Entergy's 2025 Performance Report said construction began in December 2025 on Franklin Farms 1 and Franklin Farms 2.
Source: Entergy, Mar 2026
-
NextLate 2028
Richland Parish plants expected online
The date given in the August 20, 2025 Entergy release.
Source: Entergy, Aug 20, 2025
-
ExpectedEnd of 2029
Waterford 5 expected to be operational
The August 20, 2025 release said the Waterford plant is expected to be operational by the end of 2029. The later performance report also projected 2029.
Source: Entergy, Aug 20, 2025
Worth knowing
- The map counts $3.2 billion for all three plants together. The official August 20, 2025 Entergy approval release and the 2025 Performance Report reviewed for this pass do not state that dollar total, so this page does not treat $3.2 billion as an official company figure from those documents.
- The pin is approximate, near the Richland Parish site. The Waterford plant is in St. Charles Parish.
- The $3.2 billion map figure is not broken out per plant.
- Later Entergy applications for additional plants, including Westlake and Waterford 6, are separate from these three units and are not counted here.
- The late-2028 and 2029 online dates are official targets and may move.
Go deeper
Last checked Nov 23, 2026. We add a step when it happens and link the source.
Tracking saves to this device only. No account, no email, free.