Track your favorite projects · Infrastructure

Elgin O'Hare Western Access, I-490 Tollway

Illinois State Toll Highway Authority · West of O'Hare International Airport, between I-90 in Des Plaines and I-294 in Franklin Park, Cook and DuPage counties, Illinois

Under construction, with first ramps open

A new north-south tollway and western O'Hare access, with an official project budget of $4.269 billion and the first I-294 ramps opened in October 2026.

Show on the map: Elgin O'Hare Western Access, I-490 Tollway

Next gate

Complete the Illinois Route 390 interchange and continue I-490 north

Illinois Route 390 interchange by the end of 2027; Franklin Avenue interchange and I-490 to the north anticipated in 2029

Official 2026 Tollway materials give an end-of-2027 completion for the I-490 / Illinois Route 390 interchange and a 2029 target for the full Franklin Avenue interchange and the continuation of I-490 north.

Every step so far, and what comes next

  1. DoneSeptember 30, 2025

    Official budget stands at $4.269 billion

    The October 2025 capital report listed a $4,269,139,478 EOWA budget, with about $3.13 billion spent.

  2. DoneOctober 23, 2026

    First I-490 ramps to I-294 open

    The Tollway opened two ramps connecting I-294 to the first segment of I-490 at Franklin Avenue.

  3. NextEnd of 2027

    I-490 / Illinois Route 390 interchange completion

    The scheduled completion given on the official October 7, 2026 fact sheet.

  4. Expected2029

    Franklin Avenue interchange and I-490 north

    The anticipated opening given in the October 23, 2026 Tollway release.

Worth knowing

Go deeper

Last checked Nov 23, 2026. We add a step when it happens and link the source.

Tracking saves to this device only. No account, no email, free.