Track your favorite projects · Infrastructure
East San Fernando Valley light rail
A 6.7 mile at-grade light rail line under construction on Van Nuys Boulevard, with a $1.9 billion contract amount used on the map and completion expected in December 2031.
Show on the map: East San Fernando Valley light rail
- InvestmentSkanska's August 14, 2026 release says Skanska, in a joint venture with Stacy Witbeck, signed a contract with the Los Angeles County Metropolitan Transportation Authority for the East San Fernando Valley Light Rail Transit Project and would include its share of the USD 1.9 billion contract, worth USD 957 million, in U.S. order bookings for the third quarter of 2026. The map uses that $1.9 billion contract amount, labeled $1.9B (contract). Official Metro Board Report 2026-0266, prepared for the May 28, 2026 board meeting, recommended a Phase 2 Supplement of $1,988,038,124 to Contract No. PS89616000 with San Fernando Transit Constructors, increasing the total contract value from $442,916,240 to $2,430,954,364. That later official total contract value is not used to replace the map's $1.9 billion contract figure, and neither figure is treated as a separately sourced full program cost.Skanska, Aug 14, 2026
- Scope and scheduleThe Skanska release describes construction of a 6.7 mile, at-grade light rail line along Van Nuys Boulevard, a 26-acre rail and maintenance facility, and 11 new stations, including shade structures and utility improvements. It says work has begun and the project is expected to be completed in December 2031.Skanska, Aug 14, 2026
Next gate
Project expected to be completed
December 2031, according to the August 14, 2026 Skanska release
Skanska said work has begun and the project is expected to be completed in December 2031. This pass did not find a later official schedule change.
Every step so far, and what comes next
-
DoneMay 28, 2026
Metro board report on the Phase 2 contract supplement
Official Board Report 2026-0266 recommended a Phase 2 Supplement of $1,988,038,124, increasing the total contract value to $2,430,954,364. That official total is not used to replace the map's $1.9 billion contract figure.
Source: Los Angeles County Metropolitan Transportation Authority, May 28, 2026
-
DoneAugust 14, 2026
Skanska announces the $1.9 billion joint-venture contract
Skanska said it signed, with Stacy Witbeck, a $1.9 billion contract, the figure used on the map, and that work had begun, with completion expected in December 2031.
Source: Skanska, Aug 14, 2026
-
NextDecember 2031
Project expected to be completed
The official contractor release expects completion in December 2031.
Source: Skanska, Aug 14, 2026
Worth knowing
- The map figure is the $1.9 billion contract amount stated in Skanska's August 14, 2026 release, with Skanska's share given as $957 million. It is a contract amount, not a separately sourced full program cost.
- Official Metro Board Report 2026-0266 recommended a Phase 2 Supplement of $1,988,038,124, increasing the total contract value to $2,430,954,364. That official total is recorded here and is not used to replace the map figure. This pass cites the board report as prepared for the May 28, 2026 meeting and does not treat a later recorded vote as confirmed beyond that report.
- The primary dollar source on the map is the contractor release, not a Metro cost page. Scope and schedule above also come from that official contractor release.
Go deeper
Last checked Nov 23, 2026. We add a step when it happens and link the source.
Tracking saves to this device only. No account, no email, free.