Track your favorite projects · Energy
Evergy Viola combined cycle gas plant, Sumner County
A permitted 710 megawatt combined-cycle natural gas plant in Sumner County, approved by the Kansas Corporation Commission on July 7, 2025, with Evergy Kansas Central's official 50 percent construction cost of $788.75 million implying a full-plant figure of about $1.58 billion used on the map, and operation expected by January 1, 2029.
Show on the map: Evergy Viola combined cycle gas plant, Sumner County
- Approval and costAn official July 7, 2025 Kansas Corporation Commission news release says the Commission approved a settlement allowing Evergy Kansas Central to recover the cost of new generation facilities, including the Viola plant near Evergy's Viola Substation in Sumner County. The official release describes two 710 megawatt combined-cycle gas turbine plants and says Evergy Kansas Central and Evergy Missouri West will each have 50 percent ownership. It states that the cost of construction to Evergy Kansas Central is estimated at $788.75 million for the Viola plant. Twice that official 50 percent share is $1,577,500,000, the basis for the $1.58 billion figure used on the map.Kansas Corporation Commission, Jul 7, 2025
- Schedule and a separate plantThe same official release says the Viola plant is expected to operate by January 1, 2029. It also describes a separate 710 megawatt McNew plant in Reno County, expected to operate by January 1, 2030, with an official Evergy Kansas Central construction cost of $800.52 million. The McNew plant is not included in this pin.Kansas Corporation Commission, Jul 7, 2025
Next gate
Commercial operation expected
January 1, 2029, according to the official July 7, 2025 KCC release
The official Commission release says the Viola plant is expected to operate by January 1, 2029. This pass did not find a later official construction-start confirmation in that release. The map pin remains listed as permitted.
Every step so far, and what comes next
-
DoneJuly 7, 2025
Commission approves the Viola settlement and an official $788.75 million 50 percent share
The official KCC release said the Commission approved a settlement for the 710 megawatt Viola plant in Sumner County, with Evergy Kansas Central's construction cost estimated at $788.75 million for a 50 percent share, the basis for the $1.58 billion map figure, and operation expected by January 1, 2029.
-
NextJanuary 1, 2029, according to the official July 7, 2025 release
Commercial operation expected
The official release says the Viola plant is expected to operate by January 1, 2029. The map pin remains listed as permitted.
Worth knowing
- The map figure of about $1.58 billion is twice the official $788.75 million construction cost to Evergy Kansas Central for its 50 percent share, as stated in the July 7, 2025 KCC release. This page does not invent a separately stated official full-plant total beyond that arithmetic from the official share.
- The McNew plant approved in the same official release is a separate project and is not added to this pin. A solar facility also approved that day is likewise not included.
- This pass did not find a later official construction-start confirmation in the July 7, 2025 release. The map pin remains listed as permitted, and this page does not change any map stage field.
Go deeper
Last checked Nov 24, 2026. We add a step when it happens and link the source.
Tracking saves to this device only. No account, no email, free.