Track your favorite projects · Energy
Expedition Generating Station
A proposed up to 1,540 megawatt combined-cycle station with an estimated $2.4 billion capitalized investment, now before the Virginia State Corporation Commission, with official planning assumptions targeting commercial operations in the fourth quarter of 2031.
Show on the map: Expedition Generating Station
- Investment and scopeThe Virginia State Corporation Commission's September 3, 2026 Order for Notice and Hearing, quoting the July 15, 2026 application, said the total capitalized investment for the Expedition Generating Station is estimated to be $2.4 billion, the figure used on the map, consisting of approximately $950 million in equipment and procurement expenses and approximately $1.4 billion in construction and development costs, in 2026 dollars. The same official order said estimated transmission-related costs for an approximately 1.8-mile, 500 kV generation-tie line to Dominion's existing Cunningham Substation are approximately $74.5 million. That gen-tie estimate is recorded here and is not added to the $2.4 billion station figure used on the map.Virginia State Corporation Commission, Sep 3, 2026
- Facility and siteOfficial Commission materials describe a natural gas-fired combined-cycle facility with a nominal summer capacity of up to 1,540 megawatts, consisting of two natural gas-fired combustion turbine generators, two heat recovery steam generators, and two steam turbine generators, on two parcels totaling approximately 426 acres in Fluvanna County, adjacent to the Tenaska Virginia Partners Generating Station. The applicants also proposed a short new natural gas lateral, less than one-half mile long, to the Transco system. Official materials said the project was selected as part of PJM Interconnection's Reliability Resource Initiative, and estimated that the project would generate approximately $247.7 million in tax revenue to Fluvanna County over its expected 30-year life.Virginia State Corporation Commission, Jul 15, 2026
- Schedule and case statusThe July 15, 2026 application, in a formal response on in-service timing, said current planning assumptions include target energization and backfeed in the fourth quarter of 2030 to support target commercial operations in the fourth quarter of 2031. The Commission's September 3, 2026 order scheduled a hearing on January 12, 2027. This pass did not find a later official certificate decision, and the case remained an application for certificates of public convenience and necessity.Expedition Generating I, LLC and Expedition Generating II, LLC, filed with the Virginia State Corporation Commission, Jul 15, 2026
Next gate
Virginia Commission hearing on the CPCN application
January 12, 2027
The Commission's September 3, 2026 Order for Notice and Hearing scheduled a public-witness and evidentiary hearing on January 12, 2027. Official application materials target commercial operations in the fourth quarter of 2031, subject to Commission action on the certificates.
Every step so far, and what comes next
-
DoneJuly 15, 2026
Applicants filed for Virginia CPCNs
Expedition Generating I, LLC and Expedition Generating II, LLC filed with the Virginia State Corporation Commission for certificates to construct and operate the Fluvanna County combined-cycle station and associated gen-tie line.
-
DoneSeptember 3, 2026
Commission issued an order for notice and hearing
The Commission scheduled a hearing on the application for January 12, 2027, and restated the applicants' $2.4 billion estimated capitalized investment for the station.
-
NextJanuary 12, 2027
Virginia Commission hearing on the CPCN application
The official order scheduled the public-witness and evidentiary hearing for January 12, 2027. Official application materials target commercial operations in the fourth quarter of 2031.
Worth knowing
- The $2.4 billion figure is the applicants' estimated capitalized investment for the generating station in 2026 dollars, not an approved construction budget. The approximately $74.5 million gen-tie estimate is separate and is not added to the map total.
- Official planning assumptions target commercial operations in the fourth quarter of 2031. This pass did not find a more specific official construction-start date in the Commission materials reviewed.
- The tracker stage is announced, matching the map, because the certificates of public convenience and necessity were still pending in the materials reviewed. This page does not change any map usd, stage, or pledge field.