Sound Transit Federal Way Link Extension
A $2.5 billion, nearly 8-mile Link light rail extension with three new stations that opened for service on December 6, 2025.
Show on the map: Sound Transit Federal Way Link Extension
- InvestmentSound Transit's December 6, 2025 opening release described funding for the $2.5 billion project, the figure used on the map, including a $790 million federal grant agreement from the Federal Transit Administration and a $629.5 million low-interest loan from the U.S. Department of TransportationSound Transit, Dec 6, 2025
- ScopeThe official opening release said the nearly 8-mile 1 Line extension adds three new stations, at Kent Des Moines, Star Lake, and Federal Way Downtown, plus two new parking structures and a parking addition in Federal WaySound Transit, Dec 6, 2025
- OpeningService began on December 6, 2025. The official release said voters approved the extension in 2008 as part of the Sound Transit 2 ballot measure, and that the project broke ground in summer 2020. Sound Transit CEO Dow Constantine said the project finished hundreds of millions of dollars under budget, without stating a new official total in that releaseSound Transit, Dec 6, 2025
Next gate
In passenger service
Opened December 6, 2025
Official Sound Transit materials treat the Federal Way Link Extension as open and in service as of December 6, 2025. No later official construction milestone remains for this extension.
Every step so far, and what comes next
-
DoneSummer 2020
Groundbreaking
The official opening release said the project broke ground in summer 2020.
Source: Sound Transit, Dec 6, 2025
-
DoneDecember 6, 2025
Passenger service began
Sound Transit said new Link service to Federal Way began that day, adding three stations in South King County.
Source: Sound Transit, Dec 6, 2025
-
NextOpened December 6, 2025
In passenger service
Official materials treat the extension as open. No later official construction milestone remains for this project.
Source: Sound Transit, Dec 6, 2025
Worth knowing
- The map figure is the $2.5 billion project cost stated in the official opening release. That release also said the project finished hundreds of millions of dollars under budget, but it did not publish a replacement official total, so the map figure is left unchanged.
- Federal grant and loan amounts are part of the $2.5 billion project funding, not added figures.