Gaines County Combustion Turbine Project
A permitted 1,160 megawatt simple-cycle dual-fuel combustion turbine plant in Gaines County, with an official recoverable capital-cost cap of $2,228,230,202 set by the Public Utility Commission of Texas on October 15, 2026.
Show on the map: Gaines County Combustion Turbine Project
- Certificate and official cost capThe Public Utility Commission of Texas's October 15, 2026 official order in Docket 58664 amends Southwestern Public Service Company's certificate to authorize construction of the Gaines County Combustion Turbine project. Finding of fact 181 sets the capital costs for which SPS may seek recovery and a return, inclusive of AFUDC, transmission upgrade and interconnection costs, and contingencies, at a cap of $2,228,230,202, the figure used on the map. Findings 175, 179, and 180 state that the company's estimated cost, inclusive of those same items, was $2,514,495,000, that the company estimate included an unreasonably high amount of contingency, and that the Commission capped contingency at 10% in setting the official recoverable cap. The official cap, not the higher company estimate, is the map figure.Public Utility Commission of Texas, Oct 15, 2026
- Scope and scheduleFinding of fact 27 states that the project will be located in Gaines County, Texas, on a large tract of SPS-owned land along the Texas-New Mexico border, with a nameplate capacity of 1,160 megawatts, five combustion turbines with dual-fuel capability, and transmission upgrades for a new Sidewinder Substation and related interconnection. The same official finding describes a partial commercial operation date of December 2028 for up to four of the turbines, a total estimated cost of approximately $2.207 billion excluding AFUDC, and says the estimated cost and schedule were based on an April 1, 2026 construction start date. The order itself is dated October 15, 2026, after that assumed start date, and this pass did not find a later official confirmation that construction had begun. The map pin remains listed as permitted. This plant is one of several separately identified self-build facilities approved in the same docket; only this plant's official cap is included here.Public Utility Commission of Texas, Oct 15, 2026
Next gate
Partial commercial operation targeted for up to four turbines
December 2028, according to official finding of fact 27
The official October 15, 2026 order describes a partial commercial operation date of December 2028 for up to four of the five turbines. The order requires steps before construction begins, and this pass did not find a later official construction-start confirmation. The map pin remains listed as permitted.
Every step so far, and what comes next
-
DoneOctober 15, 2026
Commission authorizes the plant and sets a $2,228,230,202 official cost cap
The Public Utility Commission of Texas amended SPS's certificate to authorize the 1,160 megawatt Gaines County CT project and capped recoverable capital costs at $2,228,230,202, the figure used on the map.
-
NextDecember 2028, according to official finding of fact 27
Partial commercial operation targeted for up to four turbines
The official order describes a partial commercial operation date of December 2028 for up to four of the five turbines. The map pin remains listed as permitted.
Worth knowing
- The map figure is the official recoverable capital-cost cap of $2,228,230,202 in finding of fact 181, inclusive of AFUDC, transmission upgrade and interconnection costs, and contingencies. Official findings also state a company estimate of approximately $2.207 billion excluding AFUDC and $2,514,495,000 including AFUDC. Those higher or differently scoped official estimates are recorded here and are not used to replace the official cap used on the map.
- The same official docket also authorizes other separately identified generation projects. Those projects are not added to this pin.
- The estimated schedule in the order was based on an April 1, 2026 construction start. The order is dated October 15, 2026. This pass did not find a later official confirmation that construction had begun. The map pin remains listed as permitted, and this page does not change any map stage field.