Track your favorite projects · Pharmaceuticals
Genentech Holly Springs manufacturing facility
An approximately $2 billion first East Coast Genentech plant, officially expanded in January 2026 after an August 2025 groundbreaking, with the structural framework topped out on August 18, 2026, and operations expected by 2029.
Show on the map: Genentech Holly Springs manufacturing facility
- InvestmentGenentech announced on January 20, 2026, that it was expanding its initial investment in the new Holly Springs manufacturing facility and that the increased investment will more than double the total commitment for the company's first-ever East Coast manufacturing facility to approximately $2 billion, the figure used on the map. The official August 25, 2025 groundbreaking release had described the initial investment as estimated at more than $700 million. Official materials also place the project within Roche and Genentech's broader $50 billion U.S. manufacturing, infrastructure, and R&D commitment, a company-wide figure that is not added to the map.Genentech, Jan 20, 2026
- Scope and scheduleThe official August 25, 2025 groundbreaking release said the facility would be 700,000 square feet on a 100-acre lot, designed to support production of the company's future portfolio of metabolic medicines, including next-generation treatments for obesity, and was expected to be completed and operational by 2029. The January 20, 2026 expansion release said the added investment would build out additional production capacity and significantly increase the facility's output, with the facility still set to be operational by 2029. The official August 18, 2026 topping-out release said Genentech raised the final beam, marking completion of the manufacturing building's structural framework, and described continued on-time progress on the approximately $2 billion investment.Genentech, Aug 18, 2026
- JobsThe official August 25, 2025 release said the project would add more than 400 local manufacturing jobs when the site is operational and more than 1,500 construction jobs during development. The January 20, 2026 expansion release said the expanded investment was expected to add an additional 100 new jobs, with the project supporting more than 500 high-wage manufacturing jobs and 1,500 construction jobs. The August 18, 2026 topping-out release said the facility is expected to support more than 2,000 jobs, including more than 500 high-wage manufacturing roles and more than 1,500 construction jobs.Genentech, Aug 18, 2026
Next gate
Facility expected to be operational
2029, according to official Genentech releases
Official groundbreaking, expansion, and topping-out releases all say the facility is expected to be operational by 2029. The August 18, 2026 topping-out release said structural framework was complete and described progress as on time.
Every step so far, and what comes next
-
DoneAugust 25, 2025
Genentech and Roche broke ground
Official groundbreaking materials described a more than $700 million, 700,000 square foot first East Coast Genentech plant in Holly Springs, expected to be operational by 2029.
Source: Genentech, Aug 25, 2025
-
DoneJanuary 20, 2026
Investment more than doubled to approximately $2 billion
Genentech said the increased investment would more than double the total commitment to approximately $2 billion and would add production capacity, with the facility still expected to be operational by 2029.
Source: Genentech, Jan 20, 2026
-
DoneAugust 18, 2026
Manufacturing building topped out
Genentech raised the final beam of the manufacturing building, marking completion of the structural framework, and said progress on the approximately $2 billion investment was on time.
Source: Genentech, Aug 18, 2026
-
Next2029
Facility expected to be operational
Official Genentech releases from groundbreaking through topping out say the facility is expected to be operational by 2029.
Source: Genentech, Aug 18, 2026
Worth knowing
- The map counts the later official total of approximately $2 billion. The earlier official estimate of more than $700 million is the initial commitment before the January 2026 expansion, not a competing current total.
- The $50 billion Roche and Genentech U.S. commitment is a company-wide figure, not an addition to the Holly Springs map total.
- Official job counts were updated as the investment grew. This page records the official figures from each announcement rather than replacing earlier ones silently.
- The tracker stage is under construction, matching the map. This page does not change any map usd, stage, or pledge field.
Go deeper
Last checked Nov 23, 2026. We add a step when it happens and link the source.