Google Virginia expansion, Chesterfield campus
Google's $9 billion 2025 Virginia investment, including a new Chesterfield campus now under construction and expansions elsewhere in the state.
Show on the map: Google Virginia expansion, Chesterfield campus
- InvestmentAn additional $9 billion in Virginia through the end of 2026, announced in August 2025, for a new Chesterfield campus and expansions in Loudoun and Prince William countiesVirginia Economic Development Partnership, Aug 27, 2025
- Chesterfield campusesGoogle's November 2026 project page describes three data center campuses in Chesterfield County. The Chester campus near Meadowville Technology Park is under constructionGoogle Data Centers, Nov 2026
- Chester campusThree planned buildings. The first is scheduled for completion in late 2027, and the full campus in 2028Google Data Centers, Nov 2026
- Later campusesGoogle expects to begin construction on the Upper Magnolia campus in 2027, start Watkins Center site work in early 2027, and complete Upper Magnolia's first building in 2029Google Data Centers, Nov 2026
Next gate
Watkins Center site work
Early 2027 (company target)
Google says initial site work at the Watkins Center campus, primarily mass grading, is expected to start in early 2027. Upper Magnolia construction is also expected to begin in 2027.
Every step so far, and what comes next
-
Done2025
Chester campus construction started
Google's Chesterfield page says construction on the Chester campus began in 2025.
Source: Google Data Centers, Nov 2026
-
DoneAug 27, 2025
Virginia investment announced
Governor Youngkin announced Google's plan to invest an additional $9 billion in Virginia through the end of 2026, including a new Chesterfield data center.
Source: Virginia Economic Development Partnership, Aug 27, 2025
-
Expected2027
Upper Magnolia construction starts
Google expects to begin construction on the Upper Magnolia campus in 2027.
Source: Google Data Centers, Nov 2026
-
NextEarly 2027
Watkins Center site work
Google expects to start initial site work, primarily mass grading, at the Watkins Center campus in early 2027.
Source: Google Data Centers, Nov 2026
-
ExpectedLate 2027
First Chester building complete
The first of three planned buildings at the Chester campus is scheduled for completion in late 2027.
Source: Google Data Centers, Nov 2026
-
Expected2028
Chester campus complete
Google expects to complete the Chester campus in 2028 and to begin construction on the Watkins Center campus that year.
Source: Google Data Centers, Nov 2026
Worth knowing
- The $9 billion is a statewide figure through the end of 2026. It includes expansions at existing Loudoun and Prince William campuses, not only the new Chesterfield sites.
- The map pin sits at the new Chesterfield campus near Meadowville Technology Park.
- Job figures on Google's project page are general (thousands of construction jobs and hundreds of full-time roles) and are not used here as a precise headcount.
- Dates are company targets.