Track your favorite projects · Transmission
Grain Belt Express HVDC transmission line
An 800-mile high-voltage direct current line meant to move 5,000 megawatts across four grid regions, still in federal permitting.
Show on the map: Grain Belt Express HVDC transmission line
- Investment$11 billion in private transmission investment, per the project site and the federal permitting dashboardInvenergy (Grain Belt Express project site), Nov 23, 2026
- LineAbout 800 miles across Kansas, Missouri, Illinois and Indiana, with 5,000 megawatts of delivery capacityInvenergy, May 7, 2025
- Phase 1 contractsAbout $1.7 billion awarded to Quanta Services and Kiewit in May 2025 for the Kansas-to-Missouri segmentInvenergy, May 7, 2025
- Phase 1 lengthAbout 542 miles of 600 kV line in Kansas and Missouri, plus converter stationsFederal Permitting Dashboard, Nov 23, 2026
Next gate
Federal environmental review and permitting complete
January 18, 2027, estimated
The Federal Permitting Dashboard lists environmental review as in progress, with an estimated completion date of Jan 18, 2027.
Every step so far, and what comes next
-
DoneMay 7, 2025
Construction contracts awarded
Invenergy awarded about $1.7 billion in Phase 1 contracts to Quanta and Kiewit and said construction was targeted to start in 2026.
Source: Invenergy, May 7, 2025
-
DoneJuly 23, 2025
Loan guarantee ended
The Department of Energy terminated its conditional loan-guarantee commitment, and the federal permitting timetable was paused.
-
DoneJanuary 2026
Federal review resumed
The sponsor asked to move the project back to in-progress status. The Army Corps became the lead federal agency.
-
NextJan 18, 2027, estimated
Federal permitting complete
The dashboard's estimated completion date for environmental review and permitting.
Worth knowing
- The $11 billion figure is for the full four-state line. The map pin is at the Ford County, Kansas origin.
- Invenergy targeted a 2026 construction start for Phase 1 in May 2025, before a later pause in federal permitting.
- The Department of Energy terminated a conditional loan guarantee on July 23, 2025. Permitting later resumed with the Army Corps as lead agency.
- Permitting dates can change.
Go deeper
Last checked Nov 23, 2026. We add a step when it happens and link the source.