Greenlink Nevada transmission (West and North)
Two new 525 kilovolt lines that, with the existing One Nevada Line, form a statewide transmission triangle.
Show on the map: Greenlink Nevada
- CostAbout $4.2 billion for both lines, per NV EnergyNV Energy, Jun 2026
- Greenlink WestAbout 350 miles, Las Vegas to YeringtonNV Energy, Jun 2026
- Greenlink NorthAbout 235 miles, Ely to YeringtonNV Energy, Jun 2026
Next gate
Construction status and schedule
No date published in these sources
The Bureau of Land Management updated its construction status for Greenlink West on Oct 20, 2026, but the page does not state a schedule. The NV Energy fact sheet gives no in-service dates.
Every step so far, and what comes next
-
DoneSept 8, 2024
Federal Record of Decision for Greenlink West
The Bureau of Land Management lists a Record of Decision publication date of Sept 8, 2024 for the 472 mile Greenlink West environmental review.
-
DoneJune 2026
NV Energy publishes a $4.2 billion cost estimate
NV Energy's June 2026 fact sheet gives its latest estimated cost for the whole project at about $4.2 billion.
Source: NV Energy, Jun 2026
-
NextNo date published in these sources
Construction status and schedule
The Bureau of Land Management updated its construction status for Greenlink West on Oct 20, 2026, but the page does not state a schedule. The NV Energy fact sheet gives no in-service dates.
Worth knowing
- The map pin sits along the route in Nye County. The $4.2 billion covers both lines. The Bureau of Land Management describes Greenlink West as a 472 mile line between Las Vegas and Reno, while NV Energy describes about 350 miles from Las Vegas to Yerington.
Last checked Nov 28, 2026. We add a step when it happens and link the source.