Grid Forward Central Wisconsin 345 kV line

American Transmission Company and Xcel Energy (NSPW) · Trempealeau, Wood and Columbia counties, Wisconsin

Under construction, about 5 percent complete

A new 345 kilovolt line across central Wisconsin, with about 175 miles of older lines rebuilt along the way.

Show on the map: Grid Forward line

Next gate

Line in service

December 2030 (company plan)

ATC reports a planned December 2030 in-service date. Construction was about 5 percent complete as of its Aug 12, 2026 release.

Every step so far, and what comes next

  1. DoneDec 10, 2025

    Wisconsin regulators approve the project

    The Public Service Commission of Wisconsin issued its final decision on the Grid Forward Central Wisconsin project, with an estimated cost of about $1.6 billion.

  2. DoneQ2 2026, reported Aug 12, 2026

    Line construction begins

    ATC reports line construction began in the second quarter of 2026, the first transmission structure is installed and the project is about 5 percent complete.

  3. NextDecember 2030 (company plan)company target

    Line in service

    ATC reports a planned December 2030 in-service date.

Worth knowing

Last checked Nov 28, 2026. We add a step when it happens and link the source.