Track your favorite projects · Transmission
Grid Forward Central Wisconsin 345 kV line
A new 345 kilovolt line across central Wisconsin, with about 175 miles of older lines rebuilt along the way.
Show on the map: Grid Forward line
- CostAbout $1.6 billion, the Commission-approved estimatePublic Service Commission of Wisconsin, Dec 10, 2025
- RouteTremval, Arpin and Columbia substations, with about 175 miles of existing lines rebuiltPublic Service Commission of Wisconsin, Dec 10, 2025
- In serviceDecember 2030, as planned by ATCPublic Service Commission of Wisconsin, Dec 10, 2025
Next gate
Line in service
December 2030 (company plan)
ATC reports a planned December 2030 in-service date. Construction was about 5 percent complete as of its Aug 12, 2026 release.
Every step so far, and what comes next
-
DoneDec 10, 2025
Wisconsin regulators approve the project
The Public Service Commission of Wisconsin issued its final decision on the Grid Forward Central Wisconsin project, with an estimated cost of about $1.6 billion.
Source: Public Service Commission of Wisconsin, Dec 10, 2025
-
DoneQ2 2026, reported Aug 12, 2026
Line construction begins
ATC reports line construction began in the second quarter of 2026, the first transmission structure is installed and the project is about 5 percent complete.
-
NextDecember 2030 (company plan)company target
Line in service
ATC reports a planned December 2030 in-service date.
Source: Public Service Commission of Wisconsin, Dec 10, 2025
Worth knowing
- The cost is the estimate in the Commission's Dec 10, 2025 decision. ATC says its forecast is inside the approved range.
- The map pin sits in Wood County near the Arpin substation; the line crosses several counties.
Last checked Nov 28, 2026. We add a step when it happens and link the source.