Hanford Waste Treatment and Immobilization Plant
The plant turning Hanford's Cold War tank waste into glass, now making glass in hot commissioning.
Show on the map: Hanford Waste Treatment and Immobilization Plant
- Cost$18.5 billion, DOE's latest estimate, not counting the High-Level Waste FacilityExchange Monitor, Mar 6, 2026
- Glass madeMore than 250,000 gallons of tank waste turned to glass, over 110,000 gallons in the last quarterHanford Vit Plant (Bechtel), Oct 2026
- The wastePart of 56 million gallons stored in underground tanks a few miles from the Columbia RiverHanford Vit Plant (Bechtel), Oct 2026
- MeltersTwo 300-ton melters heat the waste with glass formers to 2,100 degrees FahrenheitHanford Vit Plant (Bechtel), Oct 2026
Next gate
Steady operations
Next several months
Bechtel says hot commissioning will continue for several more months to build a steady rhythm of operations.
Every step so far, and what comes next
-
DoneOct 2025
Hot commissioning begins
The Low-Activity Waste Facility started treating real tank waste.
-
DoneMay 2026
Last heavy lift at the HLW Facility
A 680-ton crane finished its final lift, a step toward completing the roof.
Source: U.S. Department of Energy, Office of Environmental Management, May 5, 2026
-
DoneOct 2026
250,000 gallons turned to glass
More than 39,000 gallons were vitrified in September alone.
-
NextNext several months
Steady-state operations
The goal of continued hot commissioning.
Worth knowing
- The $18.5 billion excludes the High-Level Waste Facility.
- Pin is approximate, on the Hanford Site.
Last checked Nov 23, 2026. We add a step when it happens and link the source.