Track your favorite projects · Power and data centers
Homer City Energy Campus
A former coal plant being rebuilt as a natural gas campus of up to 4.4 gigawatts, with data centers planned on the same site.
Show on the map: Homer City Energy Campus
- InvestmentMore than $10 billion planned for power infrastructure and site readinessHomer City Redevelopment, Apr 2, 2025
- PowerUp to 4.4 gigawatts from seven GE Vernova 7HA.02 turbinesHomer City Generation via Business Wire, Nov 16, 2026
- Workforce on siteMore than 2,000 skilled tradespeople and contractors as of November 2026Homer City Generation via Business Wire, Nov 16, 2026
- Planned jobsMore than 10,000 direct on-site construction jobs over an expected five-year period, and about 1,000 direct and indirect permanent positions at full capacity, covering both the power plant and the data center campusHomer City Redevelopment, Mar 26, 2026
- SiteMore than 3,200 acres at the former Homer City Generating Station, which was decommissioned on July 1, 2023Homer City Redevelopment, Apr 2, 2025
- Construction fundingMore than $1 billion funded into construction as of March 2026Homer City Redevelopment, Mar 26, 2026
Next gate
Remaining 2026 turbine deliveries
Later in 2026
The remaining five turbines are scheduled to arrive later in 2026 and throughout 2027. First power is targeted for early 2028.
Every step so far, and what comes next
-
DoneJuly 1, 2023
Coal plant decommissioned
The former Homer City Generating Station stopped operating after nearly 55 years.
-
DoneMarch 22, 2025
Stacks and cooling towers taken down
Homer City Redevelopment later said the coal plant smokestacks and cooling towers came down on this date.
-
DoneApril 2, 2025
Campus announced
Homer City Redevelopment and Kiewit announced the natural gas and data center campus, with GE Vernova supplying seven turbines.
-
DoneMarch 26, 2026
More than 1,000 workers on site
HCR and Kiewit said more than 1,000 workers were on site and that first power was targeted for early 2028. More than $1 billion had been funded into construction.
-
DoneLate September 2026
First two turbines delivered and set
Homer City Generation said the first two of seven turbines were delivered and set in late September 2026, with the first half of the site's heat recovery steam generators also installed. The workforce had grown to more than 2,000.
Source: Homer City Generation via Business Wire, Nov 16, 2026
-
NextLater in 2026
Remaining 2026 turbine deliveries
The remaining five turbines are scheduled for rail transport later in 2026 and throughout 2027.
Source: Homer City Generation via Business Wire, Nov 16, 2026
-
ExpectedEarly 2028
First power
The company's published target, as of the November 2026 turbine announcement.
Source: Homer City Generation via Business Wire, Nov 16, 2026
Worth knowing
- The more than $10 billion figure is for power infrastructure and site readiness. Data center build-out is extra and is not counted on the map.
- The April 2025 announcement targeted first power by 2027 and up to 4.5 gigawatts. Later official updates say early 2028 and up to 4.4 gigawatts.
- Planned job counts cover both the power plant and the data center campus.
- Dates are company targets.
Last checked Nov 23, 2026. We add a step when it happens and link the source.