Horseshoe Lake Unit 15
An announced approximately 755 megawatt combined-cycle natural gas unit at OG&E's existing Horseshoe Lake plant, with an official cost of approximately $1.7 billion, awaiting Oklahoma Corporation Commission preapproval after a filing on October 27, 2026.
Show on the map: Horseshoe Lake Unit 15
- Investment and filingOGE Energy's official Form 10-Q for the quarter ended September 30, 2026, filed October 27, 2026, states that on that day OG&E filed a preapproval case seeking Oklahoma Corporation Commission approval of a generation capacity construction project to install a natural gas combined-cycle unit, Unit 15, at OG&E's existing Horseshoe Lake generating facility. The official 10-Q says the project is expected to add approximately 755 megawatts of nameplate capacity at a cost of approximately $1.7 billion, the figure used on the map. This is a new unit at the existing site and is separate from already-built or separately reviewed Horseshoe Lake units.OGE Energy Corp., Oct 27, 2026
Next gate
Oklahoma Corporation Commission preapproval remains outstanding
After the official October 27, 2026 preapproval filing; no official decision was found in the 10-Q reviewed this pass
The official 10-Q reports that OG&E filed for OCC preapproval of Unit 15 on October 27, 2026. This pass did not find a later official notice in that filing that the Commission had approved the unit. The map pin remains listed as announced.
Every step so far, and what comes next
-
DoneOctober 27, 2026
OG&E files for preapproval of an approximately $1.7 billion Unit 15
The official Form 10-Q says OG&E filed an OCC preapproval case that day for a natural gas combined-cycle Unit 15 at Horseshoe Lake, expected to add about 755 megawatts of nameplate capacity at a cost of approximately $1.7 billion, the figure used on the map.
Source: OGE Energy Corp., Oct 27, 2026
-
NextAfter the official October 27, 2026 preapproval filing
Commission preapproval remains outstanding
The official 10-Q reports the filing. This pass did not find a later official notice in that document that the Commission had approved the unit. The map pin remains listed as announced.
Source: OGE Energy Corp., Oct 27, 2026
Worth knowing
- The map figure is the official wording of approximately $1.7 billion in the October 27, 2026 Form 10-Q. Later unofficial or more precise published estimates are not used to replace that official figure.
- The official 10-Q places Unit 15 in the context of a 2026 integrated resource plan that identifies broader capacity needs by the 2031 and 2032 winter season. That portfolio need is not itself an official in-service date for Unit 15, and this page does not invent one.
- This unit is separate from Horseshoe Lake Units 11 through 14. Other official cost-recovery items for those earlier units are not added to this pin. The map pin remains listed as announced, and this page does not change any map stage field.