Howard-Solstice 765 kV Transmission Line

AEP Texas and CPS Energy · A new 765-kilovolt line between CPS Energy's Howard station in Bexar County and AEP Texas's Solstice station in Pecos County, Texas

Permitted

A permitted 368.50 mile single-circuit 765-kilovolt transmission line between San Antonio and Pecos County, approved by the Public Utility Commission of Texas on September 11, 2026, with an official estimated total cost of $2,153,288,231 for route 4 mod 1.

Show on the map: Howard-Solstice 765 kV Transmission Line

Next gate

Applicants estimate construction complete in September 2030 and energization in October 2030

September and October 2030, according to official finding of fact 25

The official order records the applicants' estimates that construction of the facilities will be complete by September 2030 and that the approved transmission facilities will be energized by October 2030. This pass did not find a later official construction-start confirmation in that order. The map pin remains listed as permitted.

Every step so far, and what comes next

  1. DoneSeptember 11, 2026

    Commission approves route 4 mod 1 and an official $2,153,288,231 total

    The official order states that the Commission approved route 4 mod 1 at its September 11, 2026 open meeting and, in finding of fact 80A, that the 368.50 mile route has an estimated total cost of $2,153,288,231, the figure used on the map. The order was filed September 18, 2026.

  2. NextSeptember 2030 for estimated construction completion and October 2030 for estimated energization, according to official finding of fact 25

    Applicants estimate completion and energization

    The official order records those applicant estimates. The map pin remains listed as permitted.

Worth knowing

Go deeper

Last checked Nov 24, 2026. We add a step when it happens and link the source.