Howard-Solstice 765 kV Transmission Line
A permitted 368.50 mile single-circuit 765-kilovolt transmission line between San Antonio and Pecos County, approved by the Public Utility Commission of Texas on September 11, 2026, with an official estimated total cost of $2,153,288,231 for route 4 mod 1.
Show on the map: Howard-Solstice 765 kV Transmission Line
- Certificate and official costThe official Public Utility Commission of Texas order in Docket 59336, filed September 18, 2026, amends the certificates of AEP Texas Inc. and the City of San Antonio, acting through CPS Energy, for the Howard-to-Solstice 765-kilovolt single-circuit transmission line. Finding of fact 24B states that at the open meeting held on September 11, 2026, the Commission approved route 4 mod 1. Finding of fact 80A states that route 4 mod 1 spans 368.50 miles and has an estimated total cost of $2,153,288,231, the figure used on the map. Finding of fact 156A separately states that the estimated line cost for route 4 mod 1 is $2.15 billion, which matches that official total.Public Utility Commission of Texas, Sep 18, 2026
- Schedule and station costs not addedOfficial finding of fact 25 states that the applicants estimate they will complete construction by September 2030 and energize the approved transmission facilities by October 2030. Official finding of fact 149 states that the costs of expanding AEP Texas's Solstice substation and CPS Energy's Howard substation are estimated to be approximately $350 million for each substation. Those official approximate station figures are stated separately from the route 4 mod 1 total and are not added to this pin. This pass did not find a later official construction-start confirmation in the order. The map pin remains listed as permitted.Public Utility Commission of Texas, Sep 18, 2026
Next gate
Applicants estimate construction complete in September 2030 and energization in October 2030
September and October 2030, according to official finding of fact 25
The official order records the applicants' estimates that construction of the facilities will be complete by September 2030 and that the approved transmission facilities will be energized by October 2030. This pass did not find a later official construction-start confirmation in that order. The map pin remains listed as permitted.
Every step so far, and what comes next
-
DoneSeptember 11, 2026
Commission approves route 4 mod 1 and an official $2,153,288,231 total
The official order states that the Commission approved route 4 mod 1 at its September 11, 2026 open meeting and, in finding of fact 80A, that the 368.50 mile route has an estimated total cost of $2,153,288,231, the figure used on the map. The order was filed September 18, 2026.
-
NextSeptember 2030 for estimated construction completion and October 2030 for estimated energization, according to official finding of fact 25
Applicants estimate completion and energization
The official order records those applicant estimates. The map pin remains listed as permitted.
Worth knowing
- The map figure is the official estimated total cost of $2,153,288,231 for approved route 4 mod 1 in finding of fact 80A, labeled $2.15 billion. Official finding 156A states the estimated line cost for that route as $2.15 billion. Official finding 149 separately estimates Solstice and Howard substation expansions at approximately $350 million each. Those official station figures are not added to the map total.
- Official finding 80 states a different estimated total for unselected route 4. That official alternative-route figure is not used here.
- This pass did not find a later official construction-start confirmation in the September 2026 order. The map pin remains listed as permitted, and this page does not change any map stage field.