Hampton Roads Bridge-Tunnel Expansion
A $3.9 billion widening of nearly 10 miles of I-64, including new twin bored tunnels under the harbor, the largest highway project in Virginia history.
Show on the map: Hampton Roads Bridge-Tunnel Expansion
- Investment$3.9 billion, the figure used on the map. Official project pages call it the largest highway construction project in Virginia historyVirginia Department of Transportation, Nov 20, 2026
- ScopeImprovements along a nearly 10-mile I-64 corridor, adding a third lane and a drivable shoulder in each direction, plus new twin two-lane bored tunnels under the harbor from Hampton to Norfolk. The new tunnels will provide four lanes across the water, for a total of eight lanes of capacityVirginia Department of Transportation, May 26, 2026
- FundingThe official project page says the partnership is 92% paid for by the Hampton Roads Transportation Accountability Commission with regionally controlled funds. The about page also lists $200 million from the Commonwealth's SMART SCALE program and $108 million from VDOTVirginia Department of Transportation, Nov 20, 2026
- ProgressThe official project homepage, last updated November 20, 2026, says the tunnel boring machine, Mary, made its final breakthrough on September 24, 2025, completing the twin bored tunnels, and that two eastbound lanes were shifted onto the new South Trestle in November 2025Virginia Department of Transportation, Nov 20, 2026
Next gate
Finish tunnel interiors and remaining approach work
Work is ongoing; the official homepage and about page reviewed for this pass did not publish a single tunnel-opening date
Official 2025 and 2026 project materials describe the bored tunnels as complete and traffic already using the new South Trestle, with remaining work still under way on the corridor. This page does not assign a later official opening year that was not stated on those project pages.
Every step so far, and what comes next
-
DoneSeptember 24, 2025
Tunnel boring machine's final breakthrough
Official project materials say Mary completed the second bored tunnel with a final breakthrough on September 24, 2025.
-
DoneNovember 2025
South Trestle opened to eastbound traffic
Two eastbound lanes were shifted onto the new South Trestle connecting the South Island to the Norfolk shoreline.
-
NextAs of November 20, 2026
Finish remaining corridor and tunnel-interior work
The official project homepage describes a still-active construction project after those 2025 milestones.
Worth knowing
- The $3.9 billion figure is the official project total on VDOT's HRBT pages.
- The official homepage and about page reviewed for this pass do not state a single opening date for the new tunnels. This page does not invent one.
- The design-build team is Hampton Roads Connector Partners, a joint venture with Dragados USA as lead contractor.
Last checked Nov 23, 2026. We add a step when it happens and link the source.