Hampton Roads Bridge-Tunnel Expansion

Virginia Department of Transportation · Interstate 64 between Mallory Street in Hampton and Patrol Road in Norfolk, Virginia

Under construction

A $3.9 billion widening of nearly 10 miles of I-64, including new twin bored tunnels under the harbor, the largest highway project in Virginia history.

Show on the map: Hampton Roads Bridge-Tunnel Expansion

Next gate

Finish tunnel interiors and remaining approach work

Work is ongoing; the official homepage and about page reviewed for this pass did not publish a single tunnel-opening date

Official 2025 and 2026 project materials describe the bored tunnels as complete and traffic already using the new South Trestle, with remaining work still under way on the corridor. This page does not assign a later official opening year that was not stated on those project pages.

Every step so far, and what comes next

  1. DoneSeptember 24, 2025

    Tunnel boring machine's final breakthrough

    Official project materials say Mary completed the second bored tunnel with a final breakthrough on September 24, 2025.

  2. DoneNovember 2025

    South Trestle opened to eastbound traffic

    Two eastbound lanes were shifted onto the new South Trestle connecting the South Island to the Norfolk shoreline.

  3. NextAs of November 20, 2026

    Finish remaining corridor and tunnel-interior work

    The official project homepage describes a still-active construction project after those 2025 milestones.

Worth knowing

Last checked Nov 23, 2026. We add a step when it happens and link the source.