Gateway Hudson Tunnel Project
A new two-track rail tunnel under the Hudson River, plus a full rebuild of the old North River Tunnel.
Show on the map: Gateway Hudson Tunnel Project
- Cost$16 billion, split about 70% federal and 30% localGateway Development Commission, Jul 8, 2024
- Federal moneyA $6.88 billion FTA grant, the largest ever of its kind, plus $4.06 billion in federal loans for the local shareGateway Development Commission, Jul 8, 2024
- ProgressThe first machine had bored about 400 feet and installed more than 60 lining rings by Nov 18, 2026Gateway Development Commission, Nov 18, 2026
- First stretch5,100 feet in New Jersey from the North Bergen portal to the Hudson County Access Shaft, about a year of diggingGateway Development Commission, Nov 18, 2026
Next gate
Reach the Hudson County Access Shaft
About a year after launch
The two Palisades machines take about a year to reach the shaft, where river machines take over.
Every step so far, and what comes next
-
DoneJul 8, 2024
Full funding locked in
GDC signed the FTA grant agreement and federal loans, securing the whole $16 billion.
-
DoneOct 8, 2026
First tunnel boring machine starts
The machine for the northern tube began mining on schedule.
-
DoneNov 18, 2026
Second machine starts
Both new tunnel tubes are now under construction.
-
NextAbout a year after the Oct 2026 launch
Palisades stretch done
Machines reach the access shaft after about a year.
-
Expected2035
New tunnel in service
GDC target.
-
Expected2038
Old tunnel fully rebuilt
GDC target for the North River Tunnel rehabilitation.
Worth knowing
- Pinned once at the New Jersey portal so the bi-state project is not double counted.
- The 2035 and 2038 dates are GDC targets from 2024.
Last checked Nov 23, 2026. We add a step when it happens and link the source.