Gateway Hudson Tunnel Project

Gateway Development Commission · North Bergen, New Jersey, to New York Penn Station

Under construction, both tunnel boring machines digging

A new two-track rail tunnel under the Hudson River, plus a full rebuild of the old North River Tunnel.

Show on the map: Gateway Hudson Tunnel Project

Next gate

Reach the Hudson County Access Shaft

About a year after launch

The two Palisades machines take about a year to reach the shaft, where river machines take over.

Every step so far, and what comes next

  1. DoneJul 8, 2024

    Full funding locked in

    GDC signed the FTA grant agreement and federal loans, securing the whole $16 billion.

  2. DoneOct 8, 2026

    First tunnel boring machine starts

    The machine for the northern tube began mining on schedule.

  3. DoneNov 18, 2026

    Second machine starts

    Both new tunnel tubes are now under construction.

  4. NextAbout a year after the Oct 2026 launch

    Palisades stretch done

    Machines reach the access shaft after about a year.

  5. Expected2035

    New tunnel in service

    GDC target.

  6. Expected2038

    Old tunnel fully rebuilt

    GDC target for the North River Tunnel rehabilitation.

Worth knowing

Last checked Nov 23, 2026. We add a step when it happens and link the source.