Hugh Brinson natural gas pipeline
About 400 miles of 42 inch pipe carrying Permian gas from Waha to Maypearl, announced at about $2.7 billion, with Phase I in full service since September 1, 2026 and Phase II scheduled for the first quarter of 2027.
Show on the map: Hugh Brinson natural gas pipeline
- InvestmentEnergy Transfer's December 6, 2024 announcement said combined costs of Phase I and Phase II are expected to be approximately $2.7 billion, the figure used on the map. The company's November 3, 2026 third-quarter results said the full project is expected to come in under budget, without giving a new official totalEnergy Transfer, Dec 6, 2024
- ScopePhase I includes about 400 miles of 42 inch pipeline with a capacity of 1.5 billion cubic feet per day, from Waha to Maypearl, Texas, south of the Dallas-Fort Worth area, plus a 42 mile, 36 inch Midland Lateral connecting processing plants in Martin and Midland Counties. Phase II would add compression to increase capacity to about 2.2 billion cubic feet per dayEnergy Transfer, Dec 6, 2024
- Service datesOn November 3, 2026, Energy Transfer said Phase I of the Hugh Brinson Pipeline was placed into full service on September 1, 2026, ahead of schedule, and that Phase II remains on schedule to be completed in the first quarter of 2027Energy Transfer, Nov 3, 2026
Next gate
Phase II completion targeted
First quarter of 2027
Energy Transfer's November 3, 2026 results said Phase II remains on schedule to be completed in the first quarter of 2027, and that the full project is expected to come in under budget.
Every step so far, and what comes next
-
DoneDecember 6, 2024
Final investment decision announced at about $2.7 billion
Energy Transfer announced a positive final investment decision for the Hugh Brinson Pipeline, with combined Phase I and Phase II costs expected at about $2.7 billion.
Source: Energy Transfer, Dec 6, 2024
-
DoneSeptember 1, 2026
Phase I placed into full service
Energy Transfer said Phase I entered full service on September 1, 2026, ahead of schedule.
Source: Energy Transfer, Nov 3, 2026
-
NextFirst quarter of 2027
Phase II completion targeted
The November 3, 2026 official results said Phase II remains on schedule for the first quarter of 2027.
Source: Energy Transfer, Nov 3, 2026
Worth knowing
- The $2.7 billion figure is the combined expected cost of Phase I and Phase II from the December 6, 2024 announcement. The later official statement that the project is expected to come in under budget is not treated as a new official total, and the map figure is left unchanged.
- The map pin is at the Maypearl end of the line, not a mid-point on the 400 mile route.
- The tracker stage reflects official Phase I in-service status. The map pin remains listed as under construction, and this page does not change any map stage field.
Last checked Nov 23, 2026. We add a step when it happens and link the source.
Tracking saves to this device only. No account, no email, free.