Hunts Point Access Improvement, South Bronx

New York State Department of Transportation · Hunts Point, South Bronx, New York

Operating

A completed $1.7 billion, six-year rebuild of access to the Hunts Point Market from the Bruckner Expressway and Sheridan Boulevard, with the third and final phase finished in November 2025.

Show on the map: Hunts Point Access Improvement, South Bronx

Next gate

The project is complete

Third and final phase completed as announced on November 17, 2025

The official Governor's release announced that work had been completed on the third and final phase of the $1.7 billion project. This pass did not find a later official expansion milestone in that release.

Every step so far, and what comes next

  1. DoneOctober 2022

    Phase one concluded

    The official completion release says phase one, including new ramps to Edgewater Road from Sheridan Boulevard and the eastbound Bruckner Expressway, concluded in October 2022.

  2. DoneSummer 2023

    Phase two ended

    The official release says the second phase, which reconstructed 1.25 miles of the Bruckner Expressway and added ramps to Leggett Avenue, ended in the summer of 2023.

  3. DoneNovember 17, 2025

    State announces completion of the $1.7 billion project

    Governor Hochul announced that the third and final phase of the $1.7 billion Hunts Point Access Improvement Project, the figure used on the map, had been completed.

  4. NextAfter the official November 17, 2025 completion announcement

    The completed project remains in operation

    The official release announced that the third and final phase was complete. This pass did not find a later official expansion milestone in that release.