Hunts Point Access Improvement, South Bronx
A completed $1.7 billion, six-year rebuild of access to the Hunts Point Market from the Bruckner Expressway and Sheridan Boulevard, with the third and final phase finished in November 2025.
Show on the map: Hunts Point Access Improvement, South Bronx
- Investment and completionAn official November 17, 2025 release from the Office of the Governor of New York announced that work had been completed on the third and final phase of the $1.7 billion Hunts Point Access Improvement Project, the figure used on the map. The official release says the six-year project was overseen by the New York State Department of Transportation, created direct access to Hunts Point from both the Bruckner Expressway and Sheridan Boulevard, removed tens of thousands of commercial vehicles from local streets, and added shared-use paths and new connections to area parks and the Bronx River waterfront. It says the work was accomplished in three overlapping phases and completed under budget. The official release also describes the Hunts Point Market as generating more than $2 billion in annual economic activity, which is a market figure and is not added to the project total.Office of the Governor of New York, Nov 17, 2025
- PhasesThe same official release says phase one, which concluded in October 2022, constructed new ramps to Edgewater Road, including a two-way ramp from Sheridan Boulevard and a connection from the eastbound Bruckner Expressway, replaced four bridges over rail lines, and added a shared-use path connecting Garrison Park with Concrete Plant Park. It says the second phase, which ended in the summer of 2023, reconstructed 1.25 miles of the Bruckner Expressway and created new ramps linking the westbound Bruckner to Leggett Avenue. The November 17, 2025 announcement marks completion of the third and final phase.Office of the Governor of New York, Nov 17, 2025
Next gate
The project is complete
Third and final phase completed as announced on November 17, 2025
The official Governor's release announced that work had been completed on the third and final phase of the $1.7 billion project. This pass did not find a later official expansion milestone in that release.
Every step so far, and what comes next
-
DoneOctober 2022
Phase one concluded
The official completion release says phase one, including new ramps to Edgewater Road from Sheridan Boulevard and the eastbound Bruckner Expressway, concluded in October 2022.
-
DoneSummer 2023
Phase two ended
The official release says the second phase, which reconstructed 1.25 miles of the Bruckner Expressway and added ramps to Leggett Avenue, ended in the summer of 2023.
-
DoneNovember 17, 2025
State announces completion of the $1.7 billion project
Governor Hochul announced that the third and final phase of the $1.7 billion Hunts Point Access Improvement Project, the figure used on the map, had been completed.
-
NextAfter the official November 17, 2025 completion announcement
The completed project remains in operation
The official release announced that the third and final phase was complete. This pass did not find a later official expansion milestone in that release.
Worth knowing
- The map figure is the official $1.7 billion program total in the November 17, 2025 completion announcement. The official release says the project was completed under budget but does not state a different final dollar figure, and this page does not invent one.
- The official $2 billion annual economic activity figure describes the Hunts Point Market, not the project cost, and is not added to the map total.