Track your favorite projects · Infrastructure
Central Tri-State Tollway reconstruction, I-294
A $4 billion, 22-mile rebuild and widening of I-294, with the southern and northern sections complete and remaining work scheduled through 2027.
Show on the map: Central Tri-State Tollway reconstruction, I-294
- Investment$4 billion, the figure used on the map, from the official project page and the February 11, 2026 fact sheetIllinois State Toll Highway Authority, Nov 19, 2026
- ScopeA 22-mile reconstruction and widening from Balmoral Avenue to 95th Street, including reconfiguration of the I-290/I-88 interchange at I-294, rebuilding of the Mile Long Bridge and the BNSF Railway Bridge, and integration of Flex Lanes and SmartRoad technology. The official project page says the work is scheduled from 2018 through 2027Illinois State Toll Highway Authority, Nov 19, 2026
- Completed sectionsAn October 9, 2026 Tollway release said the southern section between I-55 and 95th Street is complete, rebuilt and widened to five lanes in both directions, and that the northern section between Balmoral Avenue and North Avenue is also complete, including SmartRoad activation and widening from four to five lanes in both directions. That release also said reconstruction of the Mile Long Bridge, the BNSF Railway Bridge, and the I-294 bridges over 87th Street and Roberts Road is completeIllinois State Toll Highway Authority, Oct 9, 2026
- Work still underwayThe official project page, with a November 19, 2026 construction update, describes ongoing roadway and bridge reconstruction between I-55 and I-88 and between North Avenue and Roosevelt Road, and ongoing work to reconfigure the I-290/I-88 interchange. An October 22, 2026 release said new lanes had opened between I-55 and Ogden Avenue, providing six lanes in both directions, with mainline work between I-88 and I-55 scheduled to continue through 2027Illinois State Toll Highway Authority, Oct 22, 2026
Next gate
Finish remaining reconstruction, including the I-290/I-88 interchange
Scheduled through 2027
Official Tollway materials schedule remaining Central Tri-State work, including the I-290/I-88 interchange and mainline reconstruction between I-88 and I-55, through 2027.
Every step so far, and what comes next
-
Done2018
Construction on the project began
The official project page and fact sheet say the $4 billion reconstruction is scheduled from 2018 through 2027, with work in the northern section beginning in June 2018.
-
DoneEnd of 2024
Southern section completed
The February 11, 2026 fact sheet and a later October 2026 official release say work between I-55 and 95th Street was completed at the end of 2024.
-
DoneOctober 2026
Northern section described as complete
An official Tollway release said the northern section between Balmoral Avenue and North Avenue had been completed, along with major bridge reconstructions.
-
DoneOctober 22, 2026
New six-lane segments opened between I-55 and Ogden Avenue
The Tollway said new lanes were open on I-294 between I-55 and Ogden Avenue, providing six lanes in both directions.
-
Next2027
Remaining work scheduled to be complete
The official project page schedules the overall project through 2027, including remaining interchange and mainline work.
Worth knowing
- The official project page says the 22-mile corridor serves more than 300,000 vehicles a day. Later official 2026 releases, including the October 9, 2026 update, say more than 220,000 vehicles travel the corridor each day.
- The February 11, 2026 fact sheet said the northern section was scheduled to be complete by the end of 2026. The later October 9, 2026 official release describes that northern section as complete.
- The 2027 completion target for remaining work may still move.
Go deeper
Last checked Nov 23, 2026. We add a step when it happens and link the source.
Tracking saves to this device only. No account, no email, free.