Central Tri-State Tollway reconstruction, I-294

Illinois State Toll Highway Authority · I-294 between Balmoral Avenue and 95th Street, Cook and DuPage counties, Illinois

Under construction

A $4 billion, 22-mile rebuild and widening of I-294, with the southern and northern sections complete and remaining work scheduled through 2027.

Show on the map: Central Tri-State Tollway reconstruction, I-294

Next gate

Finish remaining reconstruction, including the I-290/I-88 interchange

Scheduled through 2027

Official Tollway materials schedule remaining Central Tri-State work, including the I-290/I-88 interchange and mainline reconstruction between I-88 and I-55, through 2027.

Every step so far, and what comes next

  1. Done2018

    Construction on the project began

    The official project page and fact sheet say the $4 billion reconstruction is scheduled from 2018 through 2027, with work in the northern section beginning in June 2018.

  2. DoneEnd of 2024

    Southern section completed

    The February 11, 2026 fact sheet and a later October 2026 official release say work between I-55 and 95th Street was completed at the end of 2024.

  3. DoneOctober 2026

    Northern section described as complete

    An official Tollway release said the northern section between Balmoral Avenue and North Avenue had been completed, along with major bridge reconstructions.

  4. DoneOctober 22, 2026

    New six-lane segments opened between I-55 and Ogden Avenue

    The Tollway said new lanes were open on I-294 between I-55 and Ogden Avenue, providing six lanes in both directions.

  5. Next2027

    Remaining work scheduled to be complete

    The official project page schedules the overall project through 2027, including remaining interchange and mainline work.

Worth knowing

Go deeper

Last checked Nov 23, 2026. We add a step when it happens and link the source.