I-35 Capital Express Central, Austin
A rebuild of I-35 through central Austin that adds two non-tolled HOV lanes each way, lowers downtown main lanes, and removes the upper decks.
Show on the map: I-35 Capital Express Central, Austin
- Investment$5.6 billion, the figure used on the map and in TxDOT's October 31, 2024 groundbreaking releaseTexas Department of Transportation, Oct 31, 2024
- ScopeTwo non-tolled high-occupancy-vehicle managed lanes in each direction from US 290 East to SH 71 / Ben White Boulevard, lowering the main lanes from Airport Boulevard to Lady Bird Lake, removing the upper decks, and adding more than 19 miles of shared-use paths plus new bicycle and pedestrian crossingsTexas Department of Transportation, Oct 31, 2024
- Start of constructionConstruction started in October 2024 with reconstruction of the Martin Luther King Jr. Boulevard Bridge, with Harper Brothers as contractor. TxDOT broke ground on October 31, 2024. The Lady Bird Lake segment (Holly Street to SH 71 / Ben White Boulevard), with Balfour Beatty as contractor, was then slated to begin in early 2025Texas Department of Transportation, Oct 31, 2024
- Later progressA February 4, 2026 TxDOT article said the department was preparing to reconstruct the I-35 bridges over Lady Bird Lake, and that the northbound Riverside Drive exit and the Holly Street entrance and exit had been closed permanently, with a new Riverside Drive bypass lane, a temporary Holly Street exit, and a U-turn openedTexas Department of Transportation, Feb 4, 2026
- CompletionThe October 2024 groundbreaking release said construction along the entire corridor is expected to be complete in 2033, weather permittingTexas Department of Transportation, Oct 31, 2024
Next gate
Corridor construction continues
Work is underway, with completion expected in 2033
TxDOT's October 31, 2024 groundbreaking release said construction along the entire corridor is expected to be complete in 2033, weather permitting. A February 4, 2026 article said TxDOT was preparing to reconstruct the I-35 bridges over Lady Bird Lake.
Every step so far, and what comes next
-
DoneOctober 2024
Construction started on the MLK Jr. Boulevard Bridge
TxDOT said construction on the Central project started in October 2024 with reconstruction of that bridge, with Harper Brothers as contractor.
-
DoneOctober 31, 2024
Project groundbreaking
TxDOT broke ground on the $5.6 billion I-35 Capital Express Central project.
-
DoneFebruary 4, 2026
Lady Bird Lake bridge phase described as next
TxDOT said it was preparing to reconstruct the I-35 bridges over Lady Bird Lake and reported permanent closures at the northbound Riverside Drive exit and the Holly Street ramps.
-
Next2033
Corridor construction continues, completion expected
The October 2024 groundbreaking release said construction along the entire corridor is expected to be complete in 2033, weather permitting.
Worth knowing
- The map and the October 31, 2024 groundbreaking release both use $5.6 billion. A February 4, 2026 TxDOT article referred to the project as a $4.5 billion project. This page keeps the official $5.6 billion groundbreaking figure used on the map and notes the later wording.
- The 2033 completion date is weather-dependent and may move.
Last checked Nov 23, 2026. We add a step when it happens and link the source.