I-39/90/94 expansion, Madison to Wisconsin Dells
A 67-mile interstate reconstruction and expansion, approved for construction and in design, with a current-year estimate of $3.69 billion and mainline traffic anticipated in 2045.
Show on the map: I-39/90/94 expansion, Madison to Wisconsin Dells
- Investment$3.69 billion in current-year dollars, the figure used on the map, from WisDOT's August 2026 report to the Transportation Projects Commission. The same report lists a year-of-expenditure total of $4.637 billionWisconsin Department of Transportation, Aug 2026
- ScopeThe official project page says the corridor spans 67 miles in Dane, Columbia, Sauk, and Juneau counties between US 12/18 in Madison and US 12/WIS 16 in Wisconsin Dells, including 15 existing interchanges and two potential new interchanges, plus I-39 from where it splits from I-90/94 to Levee Road near Portage. The August 2026 TPC report says the project replaces deteriorating infrastructure, expands that stretch of interstate, improves interchange designs including three system interchanges, and will raise the roadway to mitigate flood riskWisconsin Department of Transportation, Nov 23, 2026
- StatusThe official project page says the environmental study is complete, the project has been approved for construction, and work is moving into final design and preparing for future construction. The August 2026 TPC report showed $3.7 million spent to date, all in design, and $0 in construction spentWisconsin Department of Transportation, Aug 2026
- Delivery and scheduleA 2025 Wisconsin Act 104 design-build method is planned for earlier delivery of critical replacements such as the Mirror Lake Bridges, which the August 2026 report said reduces year-of-expenditure costs while leaving current-year costs unchanged. That report lists the last let fiscal year as 2043 and anticipated mainline open to traffic in calendar year 2045Wisconsin Department of Transportation, Aug 2026
Next gate
Advance from final design into construction
The August 2026 TPC report shows cost-to-complete spending scheduled from fiscal 2027 through 2045, with mainline traffic anticipated in 2045
Official materials describe a project approved for construction and still in design, with no construction dollars spent as of the August 2026 report. This page does not treat major construction as started.
Every step so far, and what comes next
-
Done2025
Approved as a major project
The August 2026 TPC report lists 2025 as the approval year for the Madison to Wisconsin Dells project.
-
DoneAugust 2026
Current-year estimate held at $3.69 billion
WisDOT told the Transportation Projects Commission that the current-year cost was unchanged at $3.690 billion, with a $4.637 billion year-of-expenditure total, last let fiscal year 2043, and anticipated mainline opening in 2045.
-
NextFiscal 2027 onward
Cost-to-complete spending is scheduled to ramp up
The August 2026 expenditure schedule begins showing substantial remaining costs in fiscal 2027, with construction still unspent as of that report.
-
Expected2045
Mainline anticipated to be open to traffic
The anticipated mainline-open calendar year in the August 2026 TPC schedule.
Worth knowing
- The map counts the $3.69 billion current-year estimate. The official August 2026 year-of-expenditure figure is $4.637 billion.
- The project is approved for construction and in design. The map lists it as permitted. Construction spending in the August 2026 report was still $0.
- The 2045 mainline opening and 2043 last-let fiscal year are from the August 2026 TPC schedule and may move.
- The official project page mentions two potential new interchanges; those are not treated here as already funded or committed.
Last checked Nov 23, 2026. We add a step when it happens and link the source.