I-41 reconstruction, Appleton to De Pere
The official August 2026 Wisconsin DOT report to the Transportation Projects Commission lists a current-year estimate of $1,167.0 million for reconstructing 23 miles of I-41 from STH 96 in Appleton to CTH F in De Pere, with mainline open to traffic anticipated in fall 2029.
Show on the map: I-41 reconstruction, Appleton to De Pere
- Official cost estimateThe official August 2026 Wisconsin Department of Transportation report to the Transportation Projects Commission lists the I-41 project from STH 96 to Scheuring Road with an August 2026 TPC estimate of $1,167.0 million in current-year dollars. The official $1,167.0 million current-year estimate is the amount used on the map. The same official report shows construction cost to date of $261.4 million and a remaining estimated cost to complete of $796.4 million, for a total of $1,167.0 million.Wisconsin Department of Transportation, Aug 2026
- Official scope and scheduleThe official report says the project will reconstruct 23 miles of I-41 from STH 96 in Appleton to CTH F in De Pere in Outagamie and Brown counties, expand the number of through lanes into the median, and include work at 10 interchanges and 15 grade separation locations. The official cost and schedule summary lists anticipated mainline open to traffic in fall 2029.Wisconsin Department of Transportation, Aug 2026
Next gate
Official August 2026 report listed anticipated mainline open to traffic in fall 2029
After the official August 2026 status report, toward the anticipated fall 2029 mainline opening
The official Wisconsin DOT report lists an August 2026 current-year estimate of $1,167.0 million, shows construction cost already incurred, and anticipates mainline open to traffic in fall 2029. The map pin remains listed as under construction.
Every step so far, and what comes next
-
DoneNovember 18, 2021
Environmental document completed
The official August 2026 report says the environmental document (EA/FONSI) was completed on November 18, 2021.
-
DoneAugust 2026
Wisconsin DOT reports construction cost already incurred and a $1,167.0 million current-year estimate
The official Transportation Projects Commission report shows $261.4 million in construction cost to date, a current-year total estimate of $1,167.0 million, and anticipated mainline open to traffic in fall 2029.
-
NextAfter the official August 2026 status report, toward the anticipated fall 2029 mainline opening
Official August 2026 report listed anticipated mainline open to traffic in fall 2029
The official Wisconsin DOT report lists an August 2026 current-year estimate of $1,167.0 million, shows construction cost already incurred, and anticipates mainline open to traffic in fall 2029. The map pin remains listed as under construction.
Worth knowing
- The map figure is the official August 2026 Transportation Projects Commission current-year estimate of $1,167.0 million. This page does not change any map usd, stage, or pledge field.
- The same official report also lists $3.2 million in additional associated costs outside the Majors program, a combined current-year total of $1,170.2 million, and a year-of-expenditure total of $1,174 million. Those official figures are not used to replace the $1,167.0 million map estimate.