I-69 Ohio River Crossing, Henderson to Evansville
The official 2025 Financial Plan Annual Update for the I-69 Ohio River Crossing states that the current total estimated cost for the entire project is $1.474 billion.
Show on the map: I-69 Ohio River Crossing, Henderson to Evansville
- Official costThe official I-69 Ohio River Crossing 2025 Financial Plan Annual Update, prepared as of July 31, 2025, and transmitted with a November 12, 2025 Federal Highway Administration letter, states that the current total estimated cost for the entire I-69 ORX Project is $1.474 billion, the figure used on the map. The official total covers the whole project across Kentucky and Indiana.Kentucky Transportation Cabinet and Indiana Department of Transportation, Nov 12, 2025
- Sections and schedule in the official updateThe same official update describes three sections. Section 1, overseen by KYTC, runs from KY 425 to US 60 in Henderson. A design-build contract was awarded in December 2021, and the official update says construction commenced in 2022 and is expected to be complete by October 2025. Section 3, overseen by INDOT, covers three bridges in Indiana. The official update says a design-build procurement was awarded in November 2023, construction began in July 2024, and completion is expected by November 2026. Section 2, described as the unfunded phase, would construct a new four-lane bridge connecting Sections 1 and 3 and completing the I-69 crossing from Henderson to the Evansville area, with construction anticipated to begin in 2027 and be complete in 2031.Kentucky Transportation Cabinet and Indiana Department of Transportation, Nov 12, 2025
Next gate
Official July 31, 2025 update described Section 1 and Section 3 work underway, with Section 2 still ahead
After the official 2025 Financial Plan Annual Update
The official update, as of July 31, 2025, said Section 1 construction was expected to be complete by October 2025 and Section 3 construction, which began in July 2024, was expected to be complete by November 2026, while Section 2 construction was anticipated to begin in 2027. This pass did not find a later official confirmation in that update that Section 1 had already been completed. The map pin remains listed as under construction.
Every step so far, and what comes next
-
DoneDecember 2021
Section 1 design-build contract awarded
The official 2025 Financial Plan Annual Update says a design-build procurement for Section 1 was completed and a contract awarded in December 2021, with construction commencing in 2022.
Source: Kentucky Transportation Cabinet and Indiana Department of Transportation, Nov 12, 2025
-
DoneJuly 2024
Section 3 construction begins
The official update says a design-build procurement for Section 3 was awarded in November 2023 and that construction began in July 2024, with completion expected by November 2026.
Source: Kentucky Transportation Cabinet and Indiana Department of Transportation, Nov 12, 2025
-
NextAs of the official July 31, 2025 financial-plan update
Official July 31, 2025 update described Section 1 and Section 3 work underway, with Section 2 still ahead
The official update, as of July 31, 2025, said Section 1 construction was expected to be complete by October 2025 and Section 3 construction, which began in July 2024, was expected to be complete by November 2026, while Section 2 construction was anticipated to begin in 2027. This pass did not find a later official confirmation in that update that Section 1 had already been completed. The map pin remains listed as under construction.
Source: Kentucky Transportation Cabinet and Indiana Department of Transportation, Nov 12, 2025
Worth knowing
- The map figure is the official $1.474 billion current total estimated cost for the entire I-69 Ohio River Crossing Project, as stated in the 2025 Financial Plan Annual Update. This page does not change any map usd field.
- The official update is as of July 31, 2025. It says Section 1 construction was expected to be complete by October 2025. This pass does not treat that expected date as later confirmation that Section 1 was finished. The map pin remains listed as under construction, and this page does not change any map stage field.
Go deeper
Last checked Nov 24, 2026. We add a step when it happens and link the source.