I-95 Express Toll Lanes Northern Extension

Maryland Transportation Authority · I-95 from White Marsh Boulevard (MD 43) toward MD 24, Baltimore and Harford counties, Maryland

Under construction

MDTA's official Final Consolidated Transportation Program for fiscal years 2026 to 2031 lists a total estimated cost of $1,039,304,000 for the I-95 Express Toll Lanes Northern Extension. The section from MD 43 to MD 152 opened on December 18, 2024, and work continues to MD 24.

Show on the map: I-95 Express Toll Lanes Northern Extension

Next gate

Official CTP said the first section opened in December 2024 and that work continues from MD 152 to MD 24

After the official December 18, 2024 opening of the MD 43 to MD 152 section, while work continues to MD 24

The official MDTA CTP says the northbound Express Toll Lanes opened on December 18, 2024, from MD 43 to MD 152, and that engineering and construction continue from MD 152 to MD 24. This pass did not find an official remaining opening date in that program entry. The map pin remains listed as under construction.

Every step so far, and what comes next

  1. DoneDecember 18, 2024

    Northbound Express Toll Lanes open from MD 43 to MD 152

    The official CTP says the extended northbound I-95 Express Toll Lanes opened on December 18, 2024, from White Marsh Boulevard (MD 43) to Mountain Road (MD 152).

  2. NextAfter the official December 18, 2024 opening of the MD 43 to MD 152 section, while work continues to MD 24

    Official CTP said the first section opened in December 2024 and that work continues from MD 152 to MD 24

    The official MDTA CTP says the northbound Express Toll Lanes opened on December 18, 2024, from MD 43 to MD 152, and that engineering and construction continue from MD 152 to MD 24. This pass did not find an official remaining opening date in that program entry. The map pin remains listed as under construction.