I-10 Calcasieu River Bridge
A $2.3 billion public-private replacement of the I-10 bridge over the Calcasieu River that officially broke ground in April 2026 and is expected to open in 2031.
Show on the map: I-10 Calcasieu River Bridge
- InvestmentLouisiana DOTD's August 15, 2024 announcement said the $2.3 billion Interstate 10 Calcasieu River Bridge megaproject in Lake Charles had reached financial close and that a Notice to Proceed had been issued. State and federal funding covers $1.2 billion of the overall cost, with remaining costs covered through toll revenue. Tolls will not be charged until the new bridge is open to trafficLouisiana Department of Transportation and Development, Aug 15, 2024
- ScopeThe 2024 official announcement described a 5.5-mile corridor from near Ryan Street in Lake Charles to the I-210 and I-10 interchange in Westlake, including the new bridge and approaches, interstate roadways and ramps, service roads, and interchanges. DOTD's later official Highway Priority Program guidebook said the new bridge will include three 12-foot travel lanes in each direction, 12-foot shoulders, auxiliary lanes, electronic tolling, and enhanced lighting, and will be less steep than the existing bridgeLouisiana Department of Transportation and Development, Nov 23, 2026
- Groundbreaking and later official statusThe official DOTD Draft Fiscal Year 2027-2028 Highway Priority Program Guidebook said the project broke ground in April 2026 and is expected to open in 2031. A November 17, 2026 DOTD announcement, describing temporary closures for a $1.71 million rehabilitation of the existing bridge, still referred to the work as taking place throughout the $2.3 billion replacement projectLouisiana Department of Transportation and Development, Nov 23, 2026
Next gate
New bridge opening targeted
2031
DOTD's official Highway Priority Program guidebook says the replacement project is expected to open in 2031.
Every step so far, and what comes next
-
DoneAugust 15, 2024
Financial close and Notice to Proceed
DOTD announced financial close on the $2.3 billion public-private project and said a Notice to Proceed had been issued to Calcasieu Bridge Partners.
Source: Louisiana Department of Transportation and Development, Aug 15, 2024
-
DoneApril 2026
Official groundbreaking
DOTD's official Highway Priority Program guidebook said the project broke ground in April 2026.
Source: Louisiana Department of Transportation and Development, Nov 23, 2026
-
Next2031
New bridge opening targeted
The same official guidebook said the project is expected to open in 2031.
Source: Louisiana Department of Transportation and Development, Nov 23, 2026
Worth knowing
- The map figure is the official $2.3 billion project cost. The $1.2 billion state and federal share and later toll revenue are parts of that total, not added figures.
- The November 17, 2026 DOTD announcement describes a separate $1.71 million rehabilitation of the existing bridge, expected to finish by May 2027, not a change to the $2.3 billion replacement budget.
- The groundbreaking month comes from DOTD's official guidebook, which does not give an exact calendar day in April 2026.