I-94 East-West Corridor, Milwaukee
A reconstruction of I-94 on Milwaukee's west side, including the Stadium package, with an official August 2026 estimate of $1,710.3 million and anticipated opening to traffic in December 2035 after utility relocation delays.
Show on the map: I-94 East-West Corridor, Milwaukee
- InvestmentWisDOT's official August 2026 report to the Transportation Projects Commission lists the I-94 East-West Freeway Project current estimate, as of August 2026, at $1,710.3 million, the figure rounded to $1.71 billion on the map. The same official table shows $260.4 million already spent and $1,449.9 million estimated to complete, and attributes a 3.6 percent increase since the February 2026 estimate primarily to updated let estimates and impacts from utility relocation delays. The report also states a separate year-of-expenditure inflated total cost estimate of $1,830.8 million, which is not used to replace the official August 2026 $1,710.3 million figure used on the map.Wisconsin Department of Transportation, Aug 2026
- Scope and scheduleThe official report describes the project as reconstruction and modernization of I-94 from 70th Street to 16th Street in the City of Milwaukee, including updated estimates for the Stadium package. Cost-to-date figures in the August 2026 report show construction already underway. A schedule summary in the same official report lists a delay and anticipates the mainline open to traffic in December 2035.Wisconsin Department of Transportation, Aug 2026
Next gate
Mainline anticipated to open to traffic
December 2035, according to the official August 2026 WisDOT report
The official August 2026 report to the Transportation Projects Commission anticipates the mainline opening to traffic in December 2035, after a schedule delay tied in part to utility relocation.
Every step so far, and what comes next
-
DoneAugust 2026
Official report sets a $1,710.3 million current estimate
WisDOT's report to the Transportation Projects Commission listed a current August 2026 estimate of $1,710.3 million, the figure used on the map, and anticipated the mainline opening to traffic in December 2035.
-
NextDecember 2035
Mainline anticipated to open to traffic
The official August 2026 report anticipates the mainline opening to traffic in December 2035.
Worth knowing
- The map figure is the official August 2026 current estimate of $1,710.3 million, labeled $1.71 billion. The same official report also states an inflated year-of-expenditure total of $1,830.8 million, which is a separate official estimate and is not used to replace the map figure.
- The official report attributes the latest estimate increase primarily to updated let estimates and utility relocation delays.