Track your favorite projects · Energy
Independence Gas Plant Units 3-6
A permitted approximately 1,499 megawatt combined-cycle project with an official estimated total investment of approximately $2.6125 billion, targeted for substantial completion by December 2030.
Show on the map: Independence Gas Plant Units 3-6
- InvestmentThe Arkansas Public Service Commission's June 15, 2026 Order No. 4 in Docket 25-066-U granted Arkansas Electric Cooperative Corporation a certificate of environmental compatibility and public need for Independence Gas Plant Units 3-6. The order found that AECC presented evidence of an estimated total investment of approximately $2.6125 billion, the figure used on the map, and said that amount shall be used as the benchmark cost level going forward. The same official finding said AECC shall be responsible for approximately $1.9594 billion. Witness testimony cited in the order said municipal co-owners in Conway, West Memphis, Osceola, and Jonesboro agreed to fund 25.065 percent of total construction costs, leaving AECC with 74.935 percent. The order is not a prudence finding on final cost, and AECC's share is not used in place of the official total-project benchmark.Arkansas Public Service Commission, Jun 15, 2026
- ScopeThe official order describes two combined-cycle blocks, Independence Gas Plant Units Three through Six, with a nominal generation output of approximately 1,499 megawatts, using natural gas as the primary fuel and ultra-low sulfur diesel as backup, at the existing Independence plant site, reusing some existing coal-plant facilities to the extent practicable. Related facilities under the same certificate include a new on-site 500 kV and 161 kV collector yard interconnecting with the existing Entergy Arkansas substation, and an approximately eight-mile lateral natural gas pipeline to a Natural Gas Pipeline Company of America transmission line east of the site. Those related facilities are not pinned separately and are not added as a second map total.Arkansas Public Service Commission, Jun 15, 2026
- ScheduleThe official order cites AECC testimony that engineering, design, and procurement activities would continue through the first quarter of 2027, and that the construction schedule for the two combined-cycle blocks is targeted for substantial completion by December 2030. AECC's October 1, 2026 second quarterly report said the company expected to receive a Rural Utilities Service Finding of No Significant Impact within the next two weeks and expected to begin construction activities once that finding was issued, on or before October 15, 2026. This pass, in late November 2026, did not find a later official report confirming that construction had begun.Arkansas Electric Cooperative Corporation, filed with the Arkansas Public Service Commission, Oct 1, 2026
Next gate
Two combined-cycle blocks targeted for substantial completion
December 2030, according to testimony cited in the June 15, 2026 order
Official materials target substantial completion of the two combined-cycle blocks by December 2030. The October 1, 2026 quarterly report expected construction to begin on or before October 15, 2026, after a Rural Utilities Service finding, but this pass did not find a later official commencement confirmation. The map pin remains listed as permitted.
Every step so far, and what comes next
-
DoneJune 15, 2026
Arkansas Commission granted a CECPN
Order No. 4 in Docket 25-066-U granted AECC a certificate for Independence Gas Plant Units 3-6 and set approximately $2.6125 billion as the benchmark total investment going forward.
-
DoneOctober 1, 2026
AECC filed its second quarterly permits report
The official report said AECC expected a Rural Utilities Service Finding of No Significant Impact within two weeks and expected to begin construction once it was issued, on or before October 15, 2026.
-
NextDecember 2030
Two combined-cycle blocks targeted for substantial completion
Testimony cited in the June 15, 2026 order targets substantial completion of the two combined-cycle blocks by December 2030.
Worth knowing
- The map counts the official estimated total investment of approximately $2.6125 billion, which Order No. 4 set as the benchmark cost level going forward. That is not a prudence finding on final cost.
- AECC's approximately $1.9594 billion share is the cooperative's official portion, not a replacement for the total-project benchmark used on the map.
- The approximately eight-mile gas lateral and the on-site 500 kV and 161 kV collector yard are related facilities under the same certificate and are not pinned separately.
- The tracker stage is permitted, matching the map, because this pass did not find later official confirmation that construction had begun. This page does not change any map usd, stage, or pledge field.
Go deeper
Last checked Nov 23, 2026. We add a step when it happens and link the source.