Track your favorite projects · Infrastructure
Improve I-70, Blue Springs to Wentzville
A $2.8 billion program to add a third lane in each direction on nearly 200 miles of I-70, with five segments under construction and corridor completion anticipated by the end of 2030.
Show on the map: Improve I-70, Blue Springs to Wentzville
- InvestmentMoDOT's official Improve I-70 page, reviewed on November 23, 2026, says Missouri's fiscal year 2024 budget provided $2.8 billion in general revenue and bonding authority to plan, design, construct, reconstruct, rehabilitate, and repair three lanes in each direction on nearly 200 miles of I-70 from Blue Springs to Wentzville, the figure used on the mapMissouri Department of Transportation, Nov 23, 2026
- ScheduleThe same official page says the work is divided into eight project segments, plus a truck-parking project, with contracts to be awarded throughout 2029 and total completion of the corridor anticipated by the end of 2030. The map pin is near Columbia, mid corridor, because this is a statewide corridor rather than a single siteMissouri Department of Transportation, Nov 23, 2026
- Construction statusAs listed on that official page, five Improve I-70 segments are under construction: Columbia to Kingdom City, Warrenton to Wentzville, Blue Springs to Odessa, Boonville to Rocheport, and Rocheport to Columbia. Kingdom City to Warrenton was awarded in November 2026, with construction anticipated in spring or summer 2027. Odessa to Concordia and Concordia to Boonville remain upcoming awards. A separately funded I-70 closure in downtown Kansas City scheduled for 2027 is not part of this programMissouri Department of Transportation, Nov 23, 2026
Next gate
Corridor completion targeted
End of 2030
MoDOT's official program page says total completion of the corridor is anticipated by the end of 2030, with remaining contracts to be awarded by 2029.
Every step so far, and what comes next
-
DoneJuly 2024
First Improve I-70 segment entered construction
MoDOT's official page says construction on the Columbia to Kingdom City segment began in July 2024.
-
DoneAs of the official page reviewed November 23, 2026
Five segments under construction and a sixth awarded
The official page lists five segments under construction and says the Kingdom City to Warrenton segment was awarded in November 2026, with construction still ahead.
-
NextEnd of 2030
Anticipated corridor completion
MoDOT says total completion of the corridor is anticipated by the end of 2030.
Worth knowing
- The $2.8 billion figure is the fiscal year 2024 funding authorization for the Blue Springs to Wentzville third-lane program, not a sum of every later segment bid total on the program page.
- Segment cost estimates listed on the MoDOT page, such as individual design-build contract values, are parts of the program and are not added on top of the $2.8 billion map figure.
- The downtown Kansas City I-70 closure scheduled for 2027 is identified by MoDOT as a separately funded project and is not included here.
- The map pin is approximate, near Columbia in the middle of the corridor.
Go deeper
Last checked Nov 23, 2026. We add a step when it happens and link the source.