IPP Renewed gas units
Hydrogen-capable natural gas units of 840 megawatts net output that replaced coal units near Delta, with the two renewal units placed into service in late 2025. The map uses a $1.7 billion figure for the generating units only.
Show on the map: IPP Renewed gas units
- InvestmentIntermountain Power Agency's official audited financial statements for the years ended June 30, 2026 and 2025, posted in October 2026, say that during 2026 IPA declared substantial completion of the renewal gas units, Unit 3 and Unit 4, and that the amount placed into service for those units was $1,619,567,000. The map uses a $1.7 billion figure for the generating units only. That official placed-in-service amount is recorded here and is not used to replace the map figure. The official IPA project page, retrieved November 24, 2026, does not itself state a dollar figure for the units. A separate modernization of the Southern Transmission System, including converter stations whose substantial completion the same audited statements anticipate for March 2028, is not included in this pin.Intermountain Power Agency, Oct 2026
- Scope and operationsThe official IPA project page describes IPP Renewed as including retirement of the existing coal-fueled units at the 4,614-acre Intermountain Power Project site near Delta, installation of new natural gas-fueled generating units capable of using hydrogen for 840 megawatts net generation output, and later hydrogen production and storage. It says the new units were designed to use 30 percent hydrogen fuel at start-up, transitioning to 100 percent hydrogen fuel by 2045 as technology improves. IPA is the project owner, and the Los Angeles Department of Water and Power is the operating agent and project manager. The living project page still describes the new units as beginning commercial operation in July 2025. The official audited financial statements say delays in construction and testing pushed the start of operation of Unit 3 to October 10, 2025, and Unit 4 to December 9, 2025, and that the coal units remained in operation from July 1, 2025, through November 26, 2025.Intermountain Power Agency, Nov 24, 2026
Next gate
Units are in service
Unit 3 entered service on October 10, 2025, and Unit 4 on December 9, 2025, according to official audited financial statements
Official audited financial statements report that both renewal gas units have been placed into service and that IPA declared substantial completion during fiscal 2026. This pass did not find a later official expansion milestone for the generating units themselves.
Every step so far, and what comes next
-
Done2022
Construction of the renewal project began
The official IPA project page says construction began in 2022.
-
DoneOctober 10, 2025, for Unit 3, and December 9, 2025, for Unit 4
Both renewal gas units placed into service
Official audited financial statements say Unit 3 was placed into service on October 10, 2025, and Unit 4 on December 9, 2025, with $1,619,567,000 placed into service for the two units. IPA declared substantial completion during fiscal 2026.
-
NextAfter the official in-service dates
Units remain in operation
Official audited financial statements report that both renewal gas units have been placed into service. This pass did not find a later official expansion milestone for the generating units.
Worth knowing
- The map figure is $1.7 billion for the generating units only. Official audited financial statements report that $1,619,567,000 was placed into service for Unit 3 and Unit 4. That official amount is recorded here and is not used to replace the map figure.
- Modernization of the Southern Transmission System is a separate project and is not added to this pin. The same official financial statements anticipate substantial completion of the Adelanto and Intermountain converter stations in March 2028.
- The official project page, retrieved November 24, 2026, still describes commercial operation beginning in July 2025. Official audited financial statements give later actual in-service dates of October 10, 2025, and December 9, 2025, after construction and testing delays.
Last checked Nov 24, 2026. We add a step when it happens and link the source.